Nexif Ratch Energy Secures Financial Close for Its 145MWp Bacolod Solar Power Project in the Philippines

METRO MANILA, Philippines, Oct. 14, 2024 (GLOBE NEWSWIRE) -- Nexif Ratch Energy, a leading independent power producer focused on renewable energy solutions, is thrilled to announce the financial close of its 145MWp Bacolod Solar Power Project, its second solar power project in the Philippines.

The Bacolod Solar Power Project, developed by Negros PH Solar Inc, is located across Bacolod City and Bago City in the Negros Occidental province. It is a 145 MWp ground-mounted solar photovoltaic project that will connect to NGCP’s Bacolod Substation and can potentially power to up to 52,600 households. Majority of its output will be sold through a 10-year Power Supply Agreement to a subsidiary of Aboitiz Power Corporation, with the remainder to the Wholesale Electricity Spot Market.

The project investment of more than US$100m is funded by equity from Nexif Ratch Energy and project finance facilities from Security Bank Corporation and Philippine National Bank on a limited recourse basis, with SB Capital Investment Corporation acting as the Mandated Lead Arranger and Bookrunner and PNB Capital and Investment Corporation acting as Arranger.

Construction is set to begin in October 2024, with the goal of achieving commercial operations by Q4 2025. Focus is now on an expansion on the existing site, through increased solar PV capacity of up to 20 MW and a Battery Energy Storage System.

Beyond its Calabanga and Bacolod solar projects, Nexif Ratch Energy is developing wind energy projects including the San Miguel Bay Project, a nearshore wind project with a capacity of up to 500 MW and the Lucena Project, an offshore wind project with a capacity of up to 475 MW.

Mr Surender Singh, Chairman of Nexif Ratch Energy, said “The successful financial close of our 145MWp Bacolod Solar Farm highlights the exceptional collaboration with our partners and the dedication of our local development team. We are excited to bring this project into construction. This Financial Close, in quick succession to start of commercial operations of Calabanga Solar project and rapid progress that more than 900 MW of the wind projects, showcase our commitment to Philippine renewable energy.”

Mr. Sakarin Tangkavachiranon, Director of Nexif Ratch Energy, added: “Reaching financial close for the 145 MWp NPSI solar project is a key milestone in our growth in the Philippines. This achievement, along with the start of commercial operations for our CARE solar project, lays a strong foundation for accelerating the development of our offshore wind projects in the country.”

For more information, please visit www.nexifratch.com.

About Nexif Ratch Energy:

Nexif Ratch Energy is a renewable energy company that originates, acquires, develops, constructs, and operates power projects in the Asia Pacific region. Headquartered in Singapore with regional offices across Southeast Asia, the Company has a 298 MW portfolio of operating and under construction hydro, solar and wind assets and a development pipeline of wind, solar, and energy storage projects totaling 3.5 GW.

Nexif Ratch Energy is owned 51% by Nexif Energy (Singapore) and 49% by RATCH Group (Thailand).

Media Contact:
Chariya Poopisit
Nexif Ratch Energy
Communications@nexifratch.com


Nexif Ratch Energy Secures Financial Close for Its 145MWp Bacolod Solar Power Project in the Philippines

THỦ THUẬT HAY

Cách sử dụng tính năng Water Lock trên Apple Watch series 3 hay 2 với watchos 4

Bạn có thể sử dụng Water Lock trên Apple Watch chạy watchos 4 để nâng cao trải nghiệm tập luyện thể thao dưới nước. Đó là tính năng giúp cung cấp thêm một lá chắn bổ sung nước có thể thấm vào bên trong SmartWatch.

Nguyên nhân và cách khắc phục lỗi tai nghe bị rè

Driver sau một thời gian sử dụng có thể bị xung đột với app nào đó mà chúng ta không hay biết. Thường hay diễn ra khi bạn cài phần mềm nào đó sử dụng âm thanh vào máy tính, hoặc khi bạn vừa cài driver của một phần cứng

Cách làm sao để màn hình Laptop luôn sáng

Đối với những người thường xuyên làm việc trước màn hình máy tính thì việc màn hình thường xuyên tắt gây ra sự khó chịu tột cùng, để khắc phục điều ngày họ thường cài đặt thời gian chờ từ 20 đến 30 phút.

Hướng dẫn cách cài đặt file xapk trong NoxPlayer

File xapk là gì? Nếu bạn tải file xapk cho một số game nặng từ Internet và muốn cài đặt nó trên NoxPlayer, vậy thì xem hướng dẫn sau nhé.

Cách khắc phục lỗi laptop không nhận tai nghe

Đây là nguyên nhân dễ nhận thấy nhất. Bạn chỉ cần kiểm tra bằng cách kết nối với các thiết bị khác như Smartphone hay loa Bluetooth,... để xem tai nghe có hoạt động không là được.

ĐÁNH GIÁ NHANH

Một số mẹo sử dụng Samsung Galaxy Z Fold3 5G giúp bạn có được trải nghiệm tuyệt vời hơn

Galaxy Z Fold3 5G – Smartphone màn hình gập cao cấp nhất hiện nay được tích hợp rất nhiều tính năng ưu việt hỗ trợ làm việc hiệu quả hơn. Để có được những trải nghiệm tuyệt nhất Bạn nên bỏ túi cho mình 1 số mẹo sử dụng

Đánh giá Toyota Avanza 2018 1.5AT 7 chỗ – chật hẹp và yếu hay không?

Với mức giá 593 triệu đồng, nhưng vẫn cung cấp 7 chỗ ngồi, Toyota Avanza thực hiện nhiệm vụ lấp vào khoảng trống bên dưới mẫu xe đàn anh Fortuner. Cũng giống như chiếc xe Mitsubishi Xpander vừa ra mắt, đây sẽ là lựa

Đánh giá Wiko View XL- Smartphonemàn hình Fullview tỉ lệ 18:9 giá 5 triệu

5 triệu đồng là mức giá mà hầu hệt người dùng sẵn lòng trả, nhưng với Wiko View XL- số tiền bạn bỏ ra thật sự “đáng đồng tiền bát gạo” .