Copenhagen Infrastructure Partners’ Zhong Neng offshore wind farm in Taiwan delivers first power

COPENHAGEN, Denmark and TAIPEI, Taiwan, June 26, 2024 (GLOBE NEWSWIRE) -- The Zhong Neng offshore wind farm, a joint venture between Copenhagen Infrastructure Partners (“CIP”) through its fund Copenhagen Infrastructure IV (“CI IV”) and China Steel Corporation (“CSC”), has today achieved a significant milestone with the delivery of first power.

Zhong Neng received local content plan approval from the Taiwan government in November 2019 and is the only second wind farm in Taiwan's offshore wind history to fulfill the highest localisation requirements. The first was the CIP-owned Changfang-Xidao offshore wind farm, which was recently inaugurated.

The first turbine on Zhong Neng was installed in May 2024 and a third of the wind turbines are now installed. Completion of all offshore installation work is expected in the third quarter of 2024 followed by full grid connection by year-end. Once fully operational, Zhong Neng will provide clean energy to approximately 300,000 households in Taiwan.

“We are very pleased to have reached this important project milestone in close collaboration with our partner, CSC. The successful delivery of first power demonstrates our joint project execution capabilities and I would like to thank all our partners and congratulate the Zhong Neng team for reaching this landmark,” said Mads Skovgaard Andersen, Partner at CIP. “Zhong Neng achieving first power and last month’s inauguration of Changfang-Xidao are both significant contributions to Taiwan’s energy transition.”

“The concerted efforts of shareholders CSC and CIP, the Zhong Neng team, and our supplier and contractor partners have ensured that all foundations were fabricated and installed - and that the electrical facility was successfully completed earlier this year. These achievements have paved the way towards successful turbine installation and power generation and offshore construction has progressed smoothly since the first turbine installation was announced in May,” Zhong Neng Chairman Wang Shyi-chin said. “We are committed to achieving full grid connection of the Zhong Neng project on schedule this year, which is not only our responsibility to our partners, but also our commitment to Taiwan's energy transition.”

Since entering Taiwan in 2017, CIP has been committed to offshore wind in the country and has invested significantly in developing Taiwan’s offshore wind projects, supply networks and fostering a strong industry ecosystem. CIP and other partners currently have three offshore wind projects in Taiwan with a combined capacity of approximately 1,400 MW: Changfang-Xidao (600 MW), Zhongneng (300 MW), and Fengmiao (500 MW).

About Copenhagen Infrastructure Partners
Founded in 2012, Copenhagen Infrastructure Partners P/S (CIP) today is the world’s largest dedicated fund manager within greenfield renewable energy investments and a global leader in offshore wind. The funds managed by CIP focus on investments in offshore and onshore wind, solar PV, biomass and energy-from-waste, transmission and distribution, reserve capacity, storage, advanced bioenergy, and Power-to-X.

CIP manages 12 funds and has to date raised approximately EUR 28 billion for investments in energy and associated infrastructure from more than 160 international institutional investors. CIP has approximately 500 employees and 12 offices around the world. For more information, visit www.cip.com


For further information, please contact: E-mail: media@cip.com Simon Mehl Augustesen, Chief Communication Officer Phone: +45 3052 6721 Email: siau@cip.com Thomas Kønig, Partner – Investor Relations Phone: +45 7070 5151 Email: tkon@cip.com


Copenhagen Infrastructure Partners’ Zhong Neng offshore wind farm in Taiwan delivers first power

THỦ THUẬT HAY

Hướng dẫn chuyển dữ liệu WhatsApp từ iPhone sang thiết bị Galaxy

Bạn đang muốn chuyển đổi các dữ liệu của WhatsApp từ iPhone sang thiết bị Galaxy? Vậy đâu là cách thực hiện nhanh chóng và tiện lợi nhất? Hãy để giúp bạn nhé!

Cách sửa lỗi Outlook There is no email program associated Windows 10

Trong quá trình sử dụng Outlook trên Windows 10, việc gặp phải mỗi số lỗi sẽ thường xuyên xảy ra, trong đó có There is no email program associated to perform the requested action.

Mở khóa bằng khuôn mặt trên smartphone Android cực nhanh và tiện lợi

Đây là tính năng có sẵn trên máy chứ không cần dùng phần mềm bên thứ ba.

Trải nghiệm ứng dụng đặt xe Go-Viet phiên bản Beta: Đối thủ đáng gờm của Grab

Như mình đã chia sẻ, chỉ những khách hàng nằm trong danh sách dùng thử mới có thể gọi xe và có đường link cài đặt áp riêng tuỳ vào hệ điều hành đang sử dụng. Vì vậy các bạn sẽ không thể tìm thấy ứng dụng này trên

Cách đem giao diện Android O lên smartphone của bạn

Mới cách đây ít hôm, Google đã phát hành phiên bản Android O cho các nhà phát triển. Tuy nhiên, nếu bạn muốn trải nghiệm giao diện của hệ điều...

ĐÁNH GIÁ NHANH

Bạn có dám bỏ 11 tỷ đồng để tậu Rolls-Royce Ghost 2011 không?

Ai có thể cầm lái một chiếc Rolls-Royce khi mới 25 tuổi? Đó là những rapper nổi tiếng hoặc những thiếu gia 'sinh ra đã ngậm thìa vàng'. Tôi chẳng là ai trong số họ, chẳng phải là 'giới 1%'. Tôi chỉ là một người làm

[Video] Tổng quan các chức năng phần mềm của LG V30

LG mô tả khá kĩ về cách mà họ làm cho bạn cảm thấy thoải mái và thân thiện, ví dụ như hiệu ứng chuyển nhẹ nhàng từ màn hình khóa vào trong homescreen, cũng như cách mà Floating Bar mới có thể thay cho màn hình phụ của

Asus Zenfone Max Pro mang lại những gì với mức giá 4.290.000

Asus Zenfone Max Pro M1 sở hữu thiết kế không quá nổi bật so với hàng loạt chiếc điện thoại ra mắt gần đây nhưng cấu hình của Zenfone Max Pro là cực ổn trong tầm giá.