Pacific Green Concludes 2023 with Huge Growth in its Battery Energy Parks Business

Dover, DE, Dec. 14, 2023 (GLOBE NEWSWIRE) -- Pacific Green Technologies, Inc. ('Pacific Green', OTCQB: PGTK) is celebrating a year of significant progress in its mission to build a global pipeline of grid-scale Battery Energy Storage Systems (BESS).

In 2023, the business has hit a series of key strategic milestones for its international pipeline of BESS sites in development or construction, which now approaches 6 GWh of energy storage capacity.

For the UK pipeline, consisting of pioneering projects, Richborough Energy Park Limited (“Richborough”), and Sheaf Energy Park Limited (“Sheaf”), Pacific Green concluded agreements that secure the long-term future of these assets as an integral part of the UK energy grid.

In June, Pacific Green completed the sale of 99.8 MW / 99.8 MWh Richborough to energy transition fund Sosteneo for an enterprise value of £74 million (US$93 million). Richborough has now been handed over to optimiser Shell for trading across the entirety of the UK’s energy markets.

In November, 249 MW / 373.5 MWh Sheaf reached financial close – securing a combined £120 million from NatWest and the UK Infrastructure Bank and becoming one of the largest project-financed BESS sites in the world. Simultaneously, a 10-year optimisation contract was secured for Sheaf with leading energy provider SSE, and Pacific Green entered into a transaction to sell 100% of its shares in the project to Sosteneo for an enterprise value of £210 million (US$258 million).

Building on these achievements, Pacific Green has successfully expanded its BESS interests into high potential markets overseas.

In Italy, Pacific Green acquired 51% of the shares in five 100 MW battery energy parks from energy originator, Sphera Energy, with the balance of shares to be acquired upon the achievement of certain milestones by Sphera. Commercial operation will commence on these projects throughout 2026, with the total capacity up to 2.8 GWh.

In Australia, Pacific Green has entered into a pair of exclusivity agreements to secure land for two major battery energy parks – the first a 1.0 GW / 2.0 GWh project in Portland, Victoria and the second a 0.5 GW / 1.0 GWh site in Limestone Coast, South Australia. Development is well underway for these projects, which will add significantly to regional BESS capacity in Southern Australia and are slated for commercial operation in 2026.

Scott Poulter, Pacific Green’s Chief Executive, said: “2023 has been a pivotal year for Pacific Green as we take huge steps to become a major global player in the battery energy storage market. The pioneering agreements we’ve secured in the past 12 months are testament to the unique combination of technology, infrastructure, and project finance expertise within our BESS team, as well as the strength of relationships we’ve built with our international manufacturing and development partners. We’re looking forward to taking these projects further in 2024 and beyond.”


About Pacific Green Technologies, Inc.:

Pacific Green is focused on addressing the world’s need for cleaner and more sustainable energy. It offers grid-scale battery energy storage systems, renewable and environmental technologies.

For more information, visit Pacific Green’s website:
www.pacificgreen.com

Notice Regarding Forward-Looking Statements:

This news release contains “forward-looking statements,” as that term is defined in Section 27A of the United States Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Statements in this news release which are not purely historical are forward-looking statements and include any statements regarding beliefs, plans, expectations or intentions regarding the future. Such forward-looking statements include, among other things, the continued development of the Project, any potential business developments and future interest in Pacific Green’s battery, solar and environmental technologies.

Actual results could differ from those projected in any forward-looking statements due to numerous factors. Such factors include, among others, the continuation of the development of the Project, general economic and political conditions. These forward-looking statements are made as of the date of this news release, and Pacific Green assumes no obligation to update the forward-looking statements, or to update the reasons why actual results could differ from those projected in the forward-looking statements. Although Pacific Green believes that the beliefs, plans, expectations and intentions contained in this news release are reasonable, there can be no assurance that such beliefs, plans, expectations or intentions will prove to be accurate. Investors should consult all the information set forth herein and should also refer to the risk factors disclosure outlined in Pacific Green’s annual report on Form 10-K for the most recent fiscal year, Pacific Green’s quarterly reports on Form 10-Q and other periodic reports filed from time-to-time with the Securities and Exchange Commission.


Scott Poulter, Chairman & CEO Pacific Green Technologies, Inc. media@pacificgreen.com


Pacific Green Concludes 2023 with Huge Growth in its Battery Energy Parks Business

THỦ THUẬT HAY

Hướng dẫn điều khiển máy tính từ xa bằng UltraViewer

UltraViewer được thiết kế để hỗ trợ khách hàng, đối tác từ xa vô cùng thuận tiện. Chỉ cần cả 2 cùng cài đặt UltraViewer, khởi động phần mềm lên, cung cấp ID và mật khẩu là bạn hoàn toàn có thể điều khiển từ xa vô cùng

Hướng dẫn tải video Youtube cho Android không cần phần mềm

Youtube là nơi mà đa số người dùng tìm tới khi muốn xem, tìm kiếm một vài đoạn video clip nào đó. Thông thường, nếu xem Youtube trên trình duyệt và muốn download video Youtube về máy tính, chúng ta có thể sử dụng một

Anh em muốn Mod review gì ở iPhone X?

Trong bài hỏi này bọn mình muốn biết anh em muốn bọn mình sẽ review gì từ đó để bài review nó thực tế hơn nữa. Bọn mình không chắc là sẽ làm hết được yêu cầu của anh em. Nhưng sau khi có kết quả thống…

Cách kiểm tra pin đầy hay hết trong vòng một nốt nhạc

Thay vì phải tháo ra lắp vào thiết bị như thông thường, bạn có thể kiểm tra pin đầy hay hết bằng cách thực hiện phương pháp ngay dưới đây.

Cách tùy chỉnh kích cỡ văn bản lớn hơn trên thiết bị Android

Với nhiều người, kích cỡ của văn bản trên điện thoại Android thường quá nhỏ, khiến việc đọc trở nên khó khăn và mắt luôn có cảm giác vô cùng mệt mỏi. Tuy nhiên, với thao tác tùy chỉnh kích cỡ văn bản lớn hơn trên thiết

ĐÁNH GIÁ NHANH

Đánh giá nhanh tai nghe không dây Samsung Gear IconX

Ra mắt trước Apple Airpod đến tận 2 tháng, Gear IconX thuộc dòng phụ kiện Gear của Samsung và là đối thủ ngang sức với thế hệ tai nghe không dây...

Audi A8L 2018: Chiếc xe tiên phong trong việc áp dụng ngôn ngữ thiết kế mới

Nếu như người em A7 Sportback nhấn mạnh hơn vào chất thể thao thì A8/A8L lại chú trọng vào vẻ sang trọng, mạnh mẽ. Ngoài sự ‘phình lên’ về kích thước, thiết kế của A8L vẫn giữ nguyên so với A8. Vẫn là bộ lưới tản nhiệt

Đánh giá bộ định tuyến không dây chuẩn 802.11n Aptek N303HU

Sản phẩm thiết kế gọn nhẹ và có đến 3 anten đẳng hướng để truyền dữ liệu cùng lúc đến thiết bị với băng thông đạt 300 Mbps.