Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn 3 cách Crack Win 10 Pro 2021 Vĩnh Viễn - Thành công 100%

Hệ điều hành Windows 10 đã được phát hành chính thức từ cuối tháng 7 năm 2015 và cho đến nay, đây là một trong những hệ điều hành được tải về nhiều nhất của Microsoft. Tuy nhiên, sau khi tải về hệ điều hành này, bạn sẽ

Cách tắt đồng bộ cuộc gọi trên iPhone với các thiết bị Apple bạn không nên bỏ qua

Bạn đang cảm thấy bị làm phiền bởi tính năng đồng bộ cuộc gọi trên iPhone với các thiết bị của Apple. Bạn muốn tắt kích hoạt tính năng này nhưng lại không biết cách. Hãy theo dõi bài viết dưới đây, team Thủ thuật của

Thêm công cụ Stickies ghi chú mới trên Windows 10

Nếu bạn đang tìm ứng dụng ghi chú mới trên máy tính Windows thì hãy thử ứng dụng Stickies mới, với nhiều tính năng hấp dẫn cũng như giao diện độc đáo.

5 lựa chọn mua điện thoại trong ngày lễ Valentine

Với thiết kế kim loại cao cấp đẹp mắt nhưng vẫn đảm bảo được độ mỏng, nhẹ, camera 'tự sướng' cực sắc nét cùng chế độ làm đẹp trứ danh, màn hình sáng đẹp, ninh mắt, chỉ nhiêu đó thôi cũng đủ làm siêu lòng chị em phụ nữ

2 ứng dụng có thể giúp hiển thị thông tin về thời tiết lên thanh menubar

Menu bar trong macOS là nơi có thế giúp anh em xem nhanh thời gian, ngày tháng hay mức pin và cũng là nơi bạn có thể access nhiều thứ như Wifi, pin, ….

ĐÁNH GIÁ NHANH

Đánh giá Sony XZ Premium - triết lý khác biệt

Thiết kế cổ điển, viền dầy và giá cao là sự lựa chọn của Sony với mẫu YZ Premium này. Có thể bạn không thích nhưng những người dùng riêng của Sony thì đều ủng hộ triết lý này.

Đánh giá Mobiistar LAI Zumbo J: Đáng giá từng xu

Có mức giá chỉ hơn 2 triệu đồng, nhưng Mobiistar LAI Zumbo J lại được trang bị kính 2,5D nhằm mang đến trải nghiệm tốt hơn cho người.

Đánh giá nhanh Huawei Y9 2019: Mặt lưng bóng bẩy, 4 màu sắc, 4 camera

Huawei Y9 2019 được trang bị màn hình tràn viền có kích thước 6,5 inch với thiết kế “tai thỏ”, trang bị thêm tấm nền IPS LCD, có độ tương phản 1500:1, độ phân giải Full HD+ 2.340 x 1.080 pixels.