Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách kích hoạt dùng thử giao diện Gmail mới được Google phát triển

Một bản cập nhật lớn của Gmail mới được Google tung ra với rất nhiều tính năng mới, đi cùng với một giao diện mới tối ưu cho người dùng. Mặc dù quá trình cập nhật vẫn chưa hoàn chỉnh tuy nhiên bây giờ chúng ta dã có

Kích hoạt bản quyền Key Microsoft Office Professional Plus 2016 vĩnh viễn | Cập nhật miễn phí

Key Office 2016 bản quyền được phát hành từ khá lâu, phiên bản Office này đã được nhiều người lựa chọn tải về và sử dụng trên máy tính của mình. Dưới đây là hướng dẫn chi tiết về cách kích hoạt Key Microsoft Office

Google Duo v27 hỗ trợ đa thiết bị với nhiều chỉnh sửa

Kể từ khi ra mắt Google Duo, nhà phát triển đã nhận về được khá nhiều lời chỉ trích về việc chỉ có thể sử dụng một thiết bị duy nhất trên một tài khoản đăng ký ở một thời điểm. Điều đó có nghĩa là một người có cả một

Hướng dẫn cách đặt vé xem phim CGV trên điện thoại 2023

Đặt vé xem phim trên app CGV sẽ giúp bạn dễ dàng quản lý vé xem phim và tích điểm để được tặng nước, bỏng ngô, cùng rất nhiều món quà hấp dẫn cho thành viên tích cực. Đặc biệt hơn chương trình khuyến mại U22 dành riêng

Smart Kit 360 - Ứng dụng đa năng với hơn 30 công cụ tích hợp sẵn cho smartphone

Về cơ bản, Smart Kit 360 giống như một ứng dụng đa năng với hơn 30 công cụ tích hợp sẵn nhằm cung cấp cho người dùng sự tiện lợi trong quá trình sử dụng, đặc biệt là các công cụ này chiếm dung lượng rất nhỏ từ bộ nhớ

ĐÁNH GIÁ NHANH

Đánh giá những điểm mới trên Galaxy S7

Galaxy S7 vừa được Samsung bán ra ở một số thị trường, đây có phải là một chiếc smartphone đáng để người dùng đầu tư trong năm nay?

Tại sao iPhone 13 lại có camera đặt chéo thay vì đặt thẳng như iPhone 12?

iPhone 13 ra mắt với thiết kế không có quá nhiều thay đổi so với iPhone 12. Điểm thay đổi lớn nhất là phần notch tai thỏ nhỏ hơn 20% và cụm camera có cách bố trí khác. Vậy tại sao iPhone 13 lại có camera đặt chéo thay

So sánh iPhone 13 và Google Pixel 6: Đâu là lựa chọn tốt nhất?

Apple ra mắt iPhone 13 đã hơn 1 tháng trong khi Google chỉ mới vừa giới thiệu Pixel 6. Cả hai cùng nằm trong phân khúc cao cấp nhưng chạy hai nền tảng hoàn toàn khác nhau, nhưng chúng lại là đối thủ cạnh tranh trực