Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

9 lỗi thường gặp khi bạn mua hoặc đang sử dụng Surface cũ

Ngày càng có nhiều người lựa chọn sử dụng máy tính bảng Surface vì những ưu điểm vượt trội mà nó mang lại cho người dùng. Tuy nhiên thực tế, khi sử dụng một thời gian thì những chiếc máy tính bắt đầu xuất hiện một số

File AIFF, AIF và AIFC là gì?

Trong bài viết này chúng ta sẽ cùng tìm hiểu xem các file AIFF, AIF và AIFC là gì? Và làm thế nào để mở, chỉnh sửa và chuyển đổi các file AIFF, AIF và AIFC.

Giới thiệu về bảng, truy vấn, form, báo cáo trong Access

CSDL của Access bao gồm 4 đối tượng: bảng, truy vấn, form và báo cáo. Kết hợp 4 đối tượng này với nhau thì có thể nhập, lưu trữ, phân tích và biên soạn dữ liệu theo cách bạn muốn.

Lỗ hổng SSL 3.0 đe dọa nghiêm trọng giao dịch số tại Việt Nam

Ngày 14/10, nhóm bảo mật của Google phát hiện một lỗ hổng bảo mật nghiêm trọng trong giao thức SSL 3.0 có thể cho phép hacker đánh cắp cookie và các dữ liệu liên quan khác nhằm chiếm tài khoản ebanking, tài khoản chứng

Sửa lỗi ‘Error 0x0000052E’ không thể kết nối với máy in trên Windows 11/10

Bạn nhận được thông báo lỗi ‘Operation failed with error 0x0000052E’ khi thực hiện lệnh in và không biết đó là lỗi gì mà khắc phục như thế nào? Dưới đây sẽ hướng dẫn các bạn cách khắc phục vấn đề.

ĐÁNH GIÁ NHANH

Đọ camera kép xóa phông giấu mặt: Xiaomi Mi A1 và Huawei Nova 2i

Trong bài viết cách đây 2 ngày, TCN đã đọ khả năng chụp ảnh từ camera thông thường của hai chiếc smartphone tầm trung đáng chú ý hiện nay đến từ hai hãi điện thoại Trung Quốc là Xiaomi và Huawei.

Đánh giá Dell XPS 13 9310: Máy tính dành riêng cho giới Doanh nhân

XPS 13 9310 là chiếc laptop 2-trong-1 cao cấp nhất trong phân khúc 13 inch dành cho doanh nhân. Đây cũng là sản phẩm đầu tiên của Dell hợp chuẩn Intel Evo, thiết kế tập trung vào giá trị cốt lõi để mang lại cảm hứng,

Đánh giá GoldTV SE1 - Bluetooth: dàn loa cho TV, smartphone

Đây là mẫu sản phẩm mới nhất của công ty loa GoldSound. Có thể thấy GoldSound tích cực ra mắt nhiều mẫu mã và chủng loại. Trong vòng vài tháng trở lại đây, công ty này đã ra mắt...