Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách bật tắt chế độ "Không làm phiền - Do not disturb" trên Galaxy J7 Prime

Chế độ 'Không làm phiền' trên điện thoại Samsung Galaxy là một trong những tính năng rất hữu ích giúp ta có thể tắt thông báo cuộc gọi hay tin nhắn đến để tránh bị làm phiền hay bị quấy rầy.

Hướng dẫn chi tiết cách chuyển ảnh thành văn bản với Convertio

Với Convertio Online, người dùng có thể chuyển hình ảnh thành văn bản, chuyển đổi định dạng âm thanh, chuyển đổi font chữ, chuyển đổi định dạng video... Ngoài việc cho phép tải lên file từ máy tính, Convertio Online

Trải nghiệm tính năng Picture-in-Picture trên Chrome 70

Chrome 70 đã chính thức ra mắt cho toàn bộ người dùng. Tính năng Picture-in-Picture đã từng được thử nghiệm trong phiên bản Chrome 69, nếu bạn muốn trải nghiệm thì hãy vào Menu > Help (Trợ giúp) > About Google

Cần hay không việc sử dụng phần mềm diệt Virus?

Ngày nay, mạng Internet đã trở thành một phần không thể thiếu trong cuộc sống của con người và một máy tính có kết nối mạng toàn cầu đều có nguy cơ rất cao nhiễm các loại virus và mã độc. Đã có nhiều tranh cãi về

Hướng dẫn bật tính năng chống ransomware được tích hợp trong Windows 10 Build 16232

Microsoft đã đưa ra một giải pháp đơn giản để phòng chống cuộc tấn công Ransomware để bảo vệ hàng triệu người dùng ngay trong hệ điều hành Windows 10. Gần đây hai cuộc tấn công ransomware mang tên WannaCry và Petya

ĐÁNH GIÁ NHANH

So sánh tốc độ iPhone X và iPhone 7 Plus

So với iPhone X, iPhone 7 Plus không thua kém là bao nhiêu cho thấy đây vẫn là một sản phẩm đỉnh cao của Apple.

Loa Bluetooth du lịch TRONSMART BANG: Sự lựa chọn tốt nhất cho bữa tiệc của bạn ?

Loa Bluetooth TRONSMART BANG là thế hệ loa di động mới nhất trong dòng Loa du lịch, được trang bị 2 subwoofers và 2 tweeter tổng công suất tối đa 60W, Có khả năng ghép đôi 100 loa cùng lúc cho âm thanh sống động hơn,

So sánh Xiaomi Redmi Note 11, Redmi Note 11 Pro và Redmi Note 11 Pro+

Nếu bạn đang phân vân bản thân nên mua Redmi Note 11, Redmi Note 11 Pro hay bản cao cấp nhất Redmi Note 11 Pro+ thì câu trả lời đang có ở trong bài phân tích này