Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách viết ghi chú, bình luận trên Google Sheets

Trên Google Sheets có tính năng viết bình luận, ghi chú trong ô dữ liệu giúp người dùng có thể nắm rõ nội dung khi làm việc với nhiều người.

Lỗi trên Instagram bất ngờ xóa tài khoản người dùng

Từ hôm thứ 5 vừa qua, nhiều người dùng Instagram không thể truy cập tài khoản của họ. Hãy cùng tìm hiểu tại sao lại xảy ra vấn đề này nhé!

Quy trình cứu dữ liệu trên Macbook thay đổi hoàn toàn với con chip T2 mới

Trong tài liệu này, Apple có nói đến rằng quy trình này sẽ được sử dụng đến khi mainboard trên máy tính bị hỏng. Tuy nhiên máy vẫn phải bật lên được và chưa hỏng nguồn.

Hướng dẫn cách đổi màu thư mục dễ dàng trên Windows 10

Bạn đã cảm thấy quen thuộc với màu sắc của những thư mục trên máy tính và muốn đổi màu cho chúng, hay chỉ đơn giản là mình đổi màu để sau này dễ nhận biết và truy cập nhanh hơn.

Microsoft phát hành bản build Windows 10 Redstone 4 Preview

Bản cập nhật Windows 10 Fall Creators Update(có tên mã là Redstone 3) dự kiến sẽ được phát hành vào tháng tới này. Đồng thời công ty cũng đang có kế hoạch bắt đầu triển khai các bản build đầu tiên cho phiên bản Windows

ĐÁNH GIÁ NHANH

Mercedes-Benz EQS 2022 - Kẻ kế thừa xứng tầm của S-Class

Với thiết lập hệ truyền động cao cấp nhất, Mercedes-Benz EQS 2022 có khả năng tăng tốc từ 0 - 100 km/h trong 4.3 giây và phạm vi hoạt động tối đa 507 km sau mỗi lần sạc.

Thiết kế OnePlus 5: không mới nhưng thân thiện, nhẹ, dễ cầm

Nếu anh không làm ra được một cái hay hơn cái có sẵn thì hãy học hỏi từ nó rồi nhúng những nét riêng của anh vào. Đây chính xác là những gì OnePlus đang làm.

Đánh giá nhanh Galaxy Z Fold5: Giá bán dự kiến khoảng 43 triệu có gì ?

Galaxy Z Fold5 là mẫu điện thoại màn hình gập kế nhiệm của Galaxy Z Fold4 với những nâng cấp về thiết kế, cấu hình và tính năng. Samsung sử dụng bản lề kiểu giọt nước để giảm khoảng cách giữa hai nửa màn hình khi gập