Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn tạo USB chạy Windows 11 trực tiếp

Mặc dù Microsoft đã từ bỏ dự án “Windows To Go” vào năm 2019. Nhưng nếu muốn bạn vẫn có thể sử dụng công cụ Rufus để tạo phiên bản “Windows to Go” của Windows 11 theo cách dưới đây.

Công bố kế hoạch cập nhật ColorOS ngày 13 tháng 10

Thời gian hiển thị public beta ở trên là thời gian mở mới nhất cho đợt tuyển dụng public beta, không phải thời gian đẩy phiên bản.

Cách đăng ký làm tài xế Grabtaxi, chạy taxi trực tuyến

Đăng ký làm tài xế Grabtaxi là cơ hội không thể tuyệt vời hơn để kiếm thêm thu nhập. Vừa làm tài xế Taxi ở công ty taxi hiện tại, bạn lại có thể đăng ký làm tài xế Grabtaxi để nhận các khách hàng của Grab một cách đơn

Hướng dẫn chuyển tất cả dữ liệu từ Google Chrome sang Firefox Quantum

Thông thường khi cài đặt Firefox sẽ hiển thị màn hình để bạn nhập dữ liệu từ các trình duyệt khác, ngay từ lúc đầu bạn khởi chạy nó.

Cách thay đổi, lấy lại mật khẩu tài khoản ViettelPay

Thường là đặt lại luôn chứ không phải là tìm lại nữa, hơn nữa nếu bạn cố đăng nhập sai mật khẩu quá 3 lần thì bạn sẽ bị khóa tài khoản và phải ra các đại lý của Viettel để mở lại tài khoản ViettelPay.

ĐÁNH GIÁ NHANH

Đánh giá Ford Ranger Raptor – Không còn “đất diễn” cho dân độ xe

Đại diện PVC là một trong số những người may mắn được tham gia sự kiện lái thử Ford Ranger Raptor tại Darwin, Australia cuối tháng 7 vừa qua. Với những cảm nhận chân thực của cá nhân, không mang tính quảng cáo hay chê

So sánh AirPods Pro và Beats Studio Buds: Gà cùng một mẹ có gì khác nhau?

Airpods Pro và Beats Studio Buds đều là hai mẫu tai nghe không dây mới nhất của Apple. Tuy nhiên, hai mẫu tai nghe này lại có rất nhiều điểm khác nhau. Vậy những điểm khác nhau đó là gì? Hãy mình đặt lên bàn cân và đi

Review Trên tay củ sạc nhanh Zendure Superport S3Pro – 65w [2 Type C + 1 Type A] model 2021

Đây là review về Trên tay củ sạc nhanh Zendure Superport S3Pro – 65w [2 Type C + 1 Type A] model 2021 của mình. Mình mua nó với giá 659000. Hi vọng phần review sẽ hữu ích cho bạn nào muốn mua nhé, nếu bạn có câu hỏi gì