Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn bấm dây mạng nhanh và chuẩn

Trong cuộc sống thường ngày, nếu các bạn muốn nối 2 máy tính với nhau, hoặc nối máy tính với modem thì sẽ phải làm thế nào?

Lướt web hiệu quả hơn với con lăn chuột

Ngoài những phím tắt dành riêng cho trình duyệt thì chúng tôi sẽ hướng dẫn các bạn thêm 1 số thủ thuật nhỏ để lướt web hiệu quả hơn bằng cách sử dụng con lăn chuột. Hãy cùng tham khảo nhé.

Hướng dẫn cách ghi đĩa CD/DVD trên Windows 10 không cần phần mềm

Thông thường, đối với những người chuyên làm nghề quay video và ghi video lên đĩa CD/DVD, họ thường mua phần mềm ghi đĩa Cyberlink Power2Go. Nó sẽ cung cấp những tính năng cao cấp bao gồm cả việc tạo đĩa Blue-ray.

Hướng dẫn hiển thị kết quả tìm kiếm trên một trang duy nhất trên trình duyệt Google Chrome

Thông thường, các kết quả tìm kiếm trên Google được hiển thị lần lượt thành các trang và bạn phải bấm vào các số phía dưới để hiển thị các kết quả...

Hướng dẫn sửa lỗi mạng máy tính bị chấm than vàng chỉ với 3 bước

Trong bài viết dưới đây, Quản Trị Mạng sẽ hướng dẫn các bạn một số bước cơ bản để khắc phục lỗi mạng dây máy tính bị báo lỗi chấm than vàng. Lỗi máy tính không vào được mạng, biểu tượng mạng Internet xuất hiện dấu chấm

ĐÁNH GIÁ NHANH

Đánh giá camera Samsung Galaxy J5 và J7 2016

Samsung Galaxy J5 và Galaxy J7 2016 đang là bộ đôi smartphone tầm trung hot nhất thị trường hiện nay, mặc dù vậy chất lượng camera của hai máy khiến chúng ta phải bất ngờ

Đánh giá loa vi tính 2.0 GoldSound GS51- Bluetooth

Nhân vật chính ngày hôm nay nay của chúng ta là mẫu loa GoldSound GS51-Bluetooth, là bản cải tiến thứ 3 của dòng loa vi tính 2.0 của công ty GoldSound.

Hiệu năng và thời lượng pin HTC U11+: Liệu có được như thông số trên giấy?

HTC U11+ đang là chiếc điện thoại cao cấp nhất của HTC. Dù HTC hiện vẫn gặp rất nhiều khó khăn trong kinh doanh nhưng không thể phủ nhận HTC U11+ là một chiếc điện thoại rất chất lượng.