Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn cách đăng ảnh trên Instagram máy tính đơn giản, nhanh chóng

Bạn thường xuyên sử dụng Instagram để đăng ảnh. Bạn muốn đăng ảnh trên Instagram máy tính nhưng lại không biết cách. Hãy theo dõi bài viết dưới đây, team Thủ thuật của sẽ hướng dẫn bạn cách để đăng ảnh trên Instagram

3 cách chặn hình ảnh từ các trang web trên Google Chrome

Nếu Chrome chạy chậm vì mất quá nhiều thời gian để tải hình ảnh thì đây là cách để chặn hình ảnh trên trang web trong trình duyệt.

Tốc độ đánh máy chuẩn là bao nhiêu?cao, thấp, trung bình

Trong xã hội ngày nay, máy tính là một phần không thể thiếu trong mọi công việc, hoạt động của con người. Kỹ năng đánh máy chính là một trong những kỹ năng cần rèn luyện thường xuyên. Vậy bạn có muốn biết tốc độ đánh

Hướng dẫn đặt xe Grab trên Google Maps

Thay vì đặt xe Grab trên ứng dụng Grab như thông thường, bạn có thể lựa chọn thực hiện việc đặt xe Grab qua ứng dụng bản đồ Google Maps. Chức năng đặt xe Grab trên Google Maps cho phép bạn gọi xe đơn giản và nhanh

2 cách nhanh chóng giúp kiểm tra tình trạng chuyến bay trên iPhone

Bạn chuẩn bị đi du lịch hay là người thường xuyên 'du hí' đây đó trên những chuyến bay? Nếu bạn muốn kiểm tra tình trạng chuyến bay của mình trên iPhone thì hãy thực hiện ngay các bước dưới đây nhé!

ĐÁNH GIÁ NHANH

Đánh giá iPhone 4s sau 5 năm sử dụng: Cũ nhưng có kĩ?

iPhone 4s là một chiến binh mạnh của Apple trong thời kì đầu của smartphone, và sau 5 năm sử dụng liệu rằng chiếc điện thoại này có còn mang lại...

Tiếp tục đánh giá Triumph T120 Black hoàn toàn mới

Triumph T120 Black 2016 sở hữu thiết kế mới với các chi tiết tinh tế hơn, là kết quả của sự thu nhặt và dung hòa phản hồi từ khách hàng cũng như sự tiếp thu và nghiên cứu những công nghệ mới. Với...

Đánh giá thời lượng pin Galaxy A7 2017: dùng cực “trâu”, sạc cực nhanh

Cùng đánh giá thời lượng pin Galaxy A7 2017 để xem với dung lượng pin tới 3.600 mAh, chiếc phablet này sẽ đem tới cho người dùng trải nghiệm như thế nào nhé!