Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cấu hình chơi GTA 5 và cách tải trên điện thoại

Dù ra mắt từ khá lâu nhưng đến nay độ nóng của game Grand Theft Auto hay GTA vẫn không hề giảm. Điều này một phần là do GTA sở hữu cốt truyện hấp dẫn, lối chơi mở, rất nhiều tùy chọn về nhân vật, nhiệm vụ, vũ khí …. để

Có nên nâng cấp lên RAM DDR5 lúc này?

Với nhiều ưu điểm vượt trội sẽ đặc biệt hấp dẫn để nâng cấp RAM của hệ thống lên DDR5. Nhưng có một số lý do mà bạn xem xem lại trước khi quyết định làm điều đó.

Hướng dẫn cài đặt Lightroom CC 2017, 2018 cho MacOS

Để cài được Adobe Lightroom CC 2017, 2018 trên iMac, Macbook chạy MacOS bạn cần có một tài khoản Adobe mới có thể tải App Creative Cloud về máy và tiến cài đặt. Bạn không nên tải các link không chính thức từ nhiều

Cách kích hoạt thanh điều hướng mới trên Android P

Ngay sau khi Android P được giới thiệu có khá nhiều thiết bị đã được phát hành bản beta để trải nghiệm những tính năng mới, trong đó đáng chú ý là thanh điều hướng được thiết kế lại.

18 thủ thuật cho công cụ chụp ảnh màn hình trên iOS 11 bạn không nên bỏ qua

Điều đầu tiên bạn có thể nhận thấy sau khi cập nhật iPhone của bạn lên iOS 11 là sự thay đổi khi chụp ảnh màn hình. Thay vì có một chút ánh sáng và âm thanh, bạn cũng sẽ thấy hình ảnh thu nhỏ của những gì bạn vừa chụp.

ĐÁNH GIÁ NHANH

Đánh giá pin Xiaomi Mi Mix 2: kém hơn thế hệ đầu tiên

Mi Mix 2 thật sự là một sự cải lùi so với Mi Mix thế hệ đầu tiên, ít nhất là ở thời gian sử dụng pin. Với viên pin nhỏ hơn (chỉ 3.400 mAh thay vì 4.400 mAh), thời gian dùng của Mi Mix 2 kém hơn so với đời trước như một

Dù giống A3s nhưng Realme 2 vẫn có thể tỏa sáng được trong tầm giá

Nếu nói Realme 2 pro có ngôn ngữ thiết kế giống hệt với mẫu OPPO A3s thì quả không sai vì phần khung lẫn mặt trước kèm cảm giác cầm nắm của chiếc smartphone này không khác gì người anh em bên phía OPPO.