Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Thiết đặt Windows 10 vào chế độ Log Off khi gập màn hình Laptop xuống

Tuy nhiên, thời gian khởi động lại laptop sau khi mở màn hình nên thường khá lâu khi Windows phải chạy lại các chương trình. Điều này khiến bạn cảm thấy mất nhiều thời gian để mở lại máy và bạn muốn thiết đặt làm sao

Cách vào Facebook trên điện thoại Android, iOS khi bị chặn

Facebook và Messenger là hai ứng dụng thường xuyên bị chặn tại các mạng ở VN, kể cả mạng internet cáp quang có dây hay mạng 3G điện thoại thì vẫn bị chặn.

Bạn biết gì về RAM cho máy trạm và Server?

Khi xảy ra lỗi truyền tệp tin như vậy với RAM non ECC sẽ có nguy cơ làm treo server hoặc server sẽ tự khởi động lại, điều này sẽ làm tê liệt hệ thống mạng của server đó gây nhiều thiệt hại. Vì vậy để đạt sự ổn định

Hướng dẫn đăng ký tài khoản Weibo không cần số điện thoại

Một trong những vấn đề lớn nhất của quá trình này chính là việc đăng ký số điện thoại (vì Weibo sẽ gửi mã xác nhận vào số điện thoại ấy) nhưng trang này lại không chấp nhận số điện thoại của Việt Nam. Vậy phải làm sao?

Windows 10 Fall Creators đã khắc phục lỗi nhảy tiếng Việt trong app Windows Store, anh em thì sao?

Mình vừa lên Win 10 Fall Creators và khi sử dụng các app như Facebook, Messenger cài đặt từ Windows Store (hay còn gọi là universal app) thì không còn bị lỗi nhảy tiếng Việt loạn xạ như trước nữa. Mình đang dùng bộ gõ

ĐÁNH GIÁ NHANH

Đánh giá Galaxy Tab A6 Spen: Trải nghiệm hoàn hảo cho dân văn phòng

Thiết kế gọn gàng, màn hình 10.1 inch PLS Full HD Tab A6 10.1 Spen được thiết kế nhựa nguyên khối với mặt lưng nhám tạo cảm giác bám tay. Các góc được bo tốt...

Đánh giá OPPO F1 Plus: Không chỉ là "chuyên gia selfie"

Đánh giá F1 Plus, chuyên gia selfie OPPO F1 Plus không chỉ nổi bật với camera trước 16 MP mà còn gây ấn tượng bởi rất nhiều yếu tố khác

Đánh giá chi tiết Nokia 2 - Smartphone "nồi đồng cối đá, pin khủng"

Máy không quá nổi bật về thông số cấu hình nhưng nếu so với mức giá chưa đến 2.5 triệu đồng thì đây vẫn là sự lựa chọn đáng dành cho những ai đang có nhu cầu mua thêm 1 chiếc điện thoại dự phòng pin tốt hay đối với