Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách ẩn khung nền của thanh dock trên iPhone sử dụng phiên bản iOS 11

Phương pháp này được thực hiện trên thiết bị và phiên bản iOS chưa hỗ trợ Jailbreak nên vẫn còn nhiều điểm giới hạn, chủ yếu là mod lại ảnh nền để che phủ khung viền của thanh Dock

Chuyển ảnh video từ điện thoại sang máy tính dùng ScanTransfer

Thay vì dùng dây cáp nối truyền thống trước đây, hiện nay đã có rất nhiều cách chuyển dữ liệu giữa điện thoại và máy tính. Sẽ không quá khó để người dùng tìm được ứng dụng chuyển file giữa PC và điện thoại.

Hướng dẫn cập nhật ứng dụng mặc định của Windows 10 Mobile

Microsoft đã chính thức xác nhận rằng Windows 10 Mobile sẽ không đi kèm tính năng Skip Ahead và hệ điều hành này sẽ chuyển sang nhánh Feature2.

Quay video màn hình smartphone cực đơn giản với cách sau

Nếu bạn muốn quay phim lại màn hình thì mình xin giới thiệu cho bạn một phần mềm cực kì tốt mà bạn không thể bỏ qua. Mời các bạn xem bài viết sao...

Cách khắc phục khi Facebook của bạn bị 'dính' Virus

Nếu Facebook bị virus hoặc tài khoản của bạn đã bị hack? Dưới đây là bốn cách mà bạn nên thử: phục hồi tài khoản của bạn, thay đổi mật khẩu của bạn, loại bỏ các ứng dụng nghi ngờ, và thực hiện quét virus.

ĐÁNH GIÁ NHANH

Với 3 camera, Samsung Galaxy A7 (2018) sẽ làm được những gì?

Samsung Galaxy A7 (2018) đang là cái tên rất hot thời điểm hiện tại khi chiếc điện thoại này có tới 3 camera sau và mức giá hợp túi tiền với đại đa số người dùng.

Đánh giá nhanh Kia Sorento - SUV 7 chỗ rẻ nhất Việt Nam với giá chưa đến 800 triệu

Thiết kế nội thất Kia Sorento 2016 lột xác hoàn toàn so với thế hệ trước đó với các chi tiết được thiết kế và bố trí gọn gàng toát lên vẻ sang trọng, chất liệu chủ đạo được sử dụng là da bọc cao cấp tô điểm bằng một số

Đánh giá Asus FX504: Không chỉ thiết kế “cool” ngầu mà còn là hiệu năng ấn tượng

Asus FX504 thực sự khiến mình ấn tượng với cái cách mà đội ngũ thiết kế của hãng tạo nên vẻ đẹp cho sản phẩm. Những họa tiết Maya cổ không chỉ tạo nên cảm giác huyền bí mà còn là dấu ấn riêng của chủ sở hữu mỗi khi