Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Nguyên nhân nào dẫn đến máy tính không nhận iPhone trong iTunes

Máy tính không nhận iPhone trong iTunes là vấn đề rất phổ biến mà nhiều người dùng đang gặp phải. Vậy nguyên nhân nào dẫn đến máy tính không nhận iPhone trong iTunes.

Hướng dẫn cách ghi đĩa CD/DVD trên Windows 10 không cần phần mềm

Thông thường, đối với những người chuyên làm nghề quay video và ghi video lên đĩa CD/DVD, họ thường mua phần mềm ghi đĩa Cyberlink Power2Go. Nó sẽ cung cấp những tính năng cao cấp bao gồm cả việc tạo đĩa Blue-ray.

Cách chỉnh âm lượng từng tab Chrome lên đến 600%

Volume Master là tiện ích cài đặt trên trình duyệt Chrome có khả năng điều chỉnh âm lượng ở từng tab riêng biệt trên trình duyệt, có thể lên tới 600%.

Cách chuyển định dạng USB từ FAT32 sang NTFS

Định dạng mặc định của USB là FAT32, tuy nhiên chúng có nhiều hạn chế so với NTFS, đơn cử là không cho phép bạn chép file lớn hơn 4GB vào USB.

16 ứng dụng iOS trị giá 36 USD đang được miễn phí

Hôm nay, TCN xin gửi đến bạn đọc danh sách ứng dụng iOS đang được miễn phí trong thời gian ngắn. Nếu các bạn quan tâm hãy nhanh tay tải về trước khi tính phí trở lại. Lưu ý là một số app cần đổi ID Apple sang khu vực

ĐÁNH GIÁ NHANH

Mổ bụng Essential Phone: phải làm lạnh mới mở ra được, rất khó sửa, 1 điểm iFixit

Đây là một trong những chiếc điện thoại khó mở nhất mà iFixit từng gặp. Để vào được bên trong, họ đã phải làm nóng rồi làm lạnh chiếc Essential Phone rồi xài dao nạy ra nhưng vẫn chưa suy chuyển, phải nạy mạnh tới mức

Trên tay màn hình Acer ET241 24-inches: Đẹp và có giá rất tốt

Về việc lựa chọn một màn hình máy tính phổ thông trên thị trường hiện nay có vô vàn sự lựa chọn. Với mức giá 3 triệu đồng thì Acer ET241 là sự lựa chọn khá tốt khi có thiết kế đẹp và chất lượng nằm ở mức khá. Thông số