Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Bạn đã biết trình duyệt hỗ trợ các tiện ích mở rộng trên Windows 10 Mobile là gì chưa?

Windows 10 Mobile mới hỗ trợ trình duyệt của bên thứ ba cung cấp các tiện ích mở rộng. Hãy cùng tìm hiểu xem trình duyệt đó là gì nhé!

Top 5 ứng dụng hát Karaoke tuyệt vời dành cho Andoird

Bạn sử dụng điện thoại thông minh cho tất cả mọi thứ, vậy tại sao không sử dụng nó để hát Karaoke? Hát những bài hát bạn yêu thích, thêm hiệu ứng cho giọng hát và thậm chí còn có nhóm hát bè. Vậy nên bài viết dưới đây

Cách quay về giao diện Chrome phiên bản cũ hơn (phiên bản Chrome 68)

Mới đây, Google đã cải tiến giao diện trình duyệt Chrome theo kiểu thiết kế Material design và tự động cập nhật lên phiên bản 69. Tuy nhiên, theo đánh giá của người dùng, phiên bản này làm trình duyệt nặng đi và giao

Hướng dẫn cách cài đặt đồng hồ Garmin trên máy tính

Việc đầu tiên khi bạn sở hữu chiếc đồng hồ Garmin là cần phải tạo tài khoản và thiết lập các tính năng cho thiết bị. Để làm được điều này chúng ta phải biết cách cài đặt đồng hồ Garmin trên máy tính. Vậy bạn hãy làm

Mở khóa màn hình thiết bị Android bằng cách chạm màn hình 2 lần

Cách thông thường mà chúng ta thường sử dụng để mở khóa màn hình thiết bị Android là nhấn nút Nguồn, hoặc trên một số thiết bị Android khác, người dùng có thể sử dụng lệnh để nói, yêu cầu mở khóa thiết bị Android.

ĐÁNH GIÁ NHANH

Nên mua Redmi Note 11 Pro+ hay Galaxy M52 5G?

Redmi Note 11 Pro+ và Galaxy M52 5G đều là hai chiếc smartphone 5G có cấu hình tốt nhất hiện nay. Vậy nên mua Redmi Note 11 Pro+ hay Galaxy M52 5G? Dưới đây là những so sánh để bạn đưa ra sự lựa chọn chính xác nhất.

Đánh giá chi tiết OPPO F7: Không chỉ còn là chiếc điện thoại chuyên về selfie

Nếu bỏ qua chất liệu thiết kế chưa sang trọng hay thiếu đi camera kép thì OPPO F7 là chiếc điên thoại toàn diện và đáng cân nhắc bậc nhất khi bạn muốn sở hữu một chiếc smartphone trong tầm giá 8 triệu đồng. Đây cũng là