Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách cập nhật iOS 15.1 Beta 2 để có trải nghiệm âm thanh sống động hơn

Apple tiếp tục phát hành iOS 15.1 Beta 2, bao gồm các cải tiến và sửa lỗi còn tồn đọng trên iOS 15. Sau đây là hướng dẫn cách cập nhật iOS 15.1 Beta 2 cho bạn...

Cách kiểm tra các quyền truy cập đang được sử dụng trên smartphone Android

Thông thường, để kiểm tra các quyền truy cập đã cấp thủ công hoặc tự động kích hoạt sau khi cài đặt ứng dụng trên smartphone Android, bạn cần phải mở trực tiếp trang quản lý apps trong mục cài đặt hệ thống khá là rắc

Tinh chỉnh Bounce, cho phép tùy biến lại hiệu ứng tắt và mở của hệ thống iOS

Bounce cho phép người dùng tùy chỉnh lại hoạt ảnh khi người dùng thực hiện một số hoạt động trên thiết bị iOS với hiệu ứng thú vị hơn, bao gồm khởi chạy / thoát ứng dụng, mở / đóng thư mục, truy cập trình đa nhiệm,

Ổ cứng hoạt động như thế nào?

Các bạn đã từng đi mua ổ cứng? Các bạn đã quá quen thuộc với ổ cứng. Vậy nhưng ổ cứng là gì và nó hoạt động thế nào, không hẳn nhiều người đã biết. Chúng ta hãy cùng xem xét vấn đề tưởng như quá quen mà vẫn hãy còn lạ

Chuyển ảnh video từ điện thoại sang máy tính dùng ScanTransfer

Thay vì dùng dây cáp nối truyền thống trước đây, hiện nay đã có rất nhiều cách chuyển dữ liệu giữa điện thoại và máy tính. Sẽ không quá khó để người dùng tìm được ứng dụng chuyển file giữa PC và điện thoại.

ĐÁNH GIÁ NHANH

Đánh giá Lenovo Z5170: Chiếc laptop ngon mà rẻ

Đánh giá Lenovo Z5170 - chiếc laptop tầm trung có màn hình lớn, thiết kế thanh lịch cùng cấu hình khá ổn trong tầm giá.

Đánh giá nhanh BMW X2: Thực sự thú vị nhưng không dành cho tất cả mọi người

Với sự xuất hiện của chiếc xe mới nhất này, gia đình X-series tại Việt Nam đã đầy đủ mọi gương mặt từ X1 đến X6. So với các mẫu xe đàn anh, BMW X2 trông nhỏ gọn hơn và thiết kế cũng đậm chất thể thao hơn với gói nâng

Đánh giá chi tiết chiến binh FullView đầu tiên của Asus: Zenfone Max Plus M1

Xét về ngoại hình, có thể thấy Zenfone Max Plus M1 mang thiết kế khá tương đồng với những người tiền nhiệm là Zenfone 4 Max hay 4 Max Pro.