Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách xóa người trong ảnh trên Xiaomi cực dễ, không cần phải tải app

Bạn đang tìm cách xóa những chi tiết không liên quan trong ảnh? Với chiếc điện thoại Xiaomi, mình sẽ chỉ các bạn cách xóa người trong ảnh không cần tải ứng dụng...

Mách bạn một số thao tác giúp tiết kiệm thời gian khi sử dụng iPhone

Sử dụng iPhone đã lâu nhưng chưa chắc người dùng đã nắm được hết những thao tác tác giúp tiết kiệm thời gian mà Apple trang bị cho điện thoại của mình.

5 bước đơn giản giúp tăng tốc độ Internet khi mạng chậm với CMD(Command Prompt )

Tốc độ internet chậm là một vấn đề không bao giờ kết thúc đối với người sử dụng internet. Tuy nhiên, nhiều vấn đề phổ biến về DNS, TCP và IP có thể được giải quyết bằng Windows Command Prompt. Dưới đây là một số lệnh

Khắc phục tình trạng Laptop liên tục không nhận được Wifi

Laptop hiện đang là một trong những thiết bị điện tử được sử dụng nhiều nhất chỉ sau smartphone

Giải mã tất cả các lỗi xuất hiện trên Google Play và cách khắc phục

Đối với người dùng Android, việc cài đặt ứng dụng từ Google Play tưởng chừng đơn giản, tuy nhiên cũng không ít lần bạn ngớ người ra bởi cửa hàng trả về lỗi với bộ mã toàn số, mà bạn lại chẳng biết vì sao, cũng như cách

ĐÁNH GIÁ NHANH

Đánh giá chi tiết Asus Zenbook UX330UA giá 750 USD

Thiết kế của Asus ZenBook UX330UA không giống với người tiền nhiệm UX305UA. Nó mỏng hơn 1/10 inch và chỉ nặng 1,18 kg nhưng bạn sẽ không nhận thấy sự khác biệt này nếu không đặt hai chiếc laptop ở cạnh nhau.