Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

5 cách bảo vệ smartphone dưới trời nắng nóng 40 độ

Khi mà tiết trời Việt Nam đã chính thức bước sang mùa hè. Bạn cần phải chuẩn bị cho mình những cách bảo vệ “dế yêu” trong lúc nhiệt độ ngoài trời chạm ngưỡng 40 độ C như hiện nay.

Tận dụng điểm mạnh của các dịch vụ lưu trữ đám mây (P1)

Trong một bài viết TrangCongNghe.com đã đăng cách đây 2 hôm, các bạn đã có thể thiết lập một 'ổ cứng trên mây' với dung lượng hơn 100GB. Tuy nhiên, để lỗi kéo người dùng, mỗi dịch vụ đều có những điểm riêng và nếu biết

Hướng dẫn sử dụng tai nghe Bluetooth đúng cách

Tai nghe Bluetooth là thiết bị kết nối không dây với các thiết bị mà không cần dây cáp, thuận tiện cho việc giải trí cũng như sử dụng trong công việc hàng ngày.

Thay màn hình iPhone 6 Plus ở đâu chính hãng, giá rẻ

Thay màn hình iPhone 6 Plus ở đâu chính hãng, giá rẻ là câu hỏi mà hầu hết ai cũng nghĩ đến khi chiếc iPhone 6 Plus yêu dấu bị rơi vỡ, bể màn hình, bể mặt kính tuy nhiên trước khi tìm kiếm đơn vị cung cấp dịch vụ thay

8 công cụ sửa lỗi DLL để tải và cài đặt file DLL tốt nhất cho Windows

Các lỗi liên quan đến file DLL là những vấn đề quan trọng, nếu không được giải quyết, có thể dẫn đến crash hoặc đóng băng và thậm chí cả màn hình màu xanh chết chóc. Do đó, giải quyết các vấn đề file DLL là cực kỳ cần

ĐÁNH GIÁ NHANH

Đây là những gì bạn có thể vọc với chiếc smartwatch DT No.1 D7 sau khi mở hộp

Bài viết này sẽ giúp bạn đọc có cái nhìn tổng quát nhất về chiếc smartwatch DT NO.1 D7. Chiếc smartwatch này được đánh giá có thời lượng pin khủng so với các sản phẩm có trên thị trường. Thông số kỹ thuật CPU: 2 nhân.

Đánh giá Xiaomi Redmi EarBuds 3 Pro: Tai nghe sở hữu chip Qualcomm xịn sò, thời lượng pin lên tới 30 tiếng, giá chưa đến 1 triệu đồng

Vừa qua, Xiaomi đã chính thức trình làng mẫu tai nghe không dây mới nhất có tên gọi Redmi EarBuds 3 Pro. Sản phẩm không chỉ sở hữu vẻ ngoài trẻ trung với nhiều tùy chọn màu cá tính, mà nó còn được trang bị nhiều tính

Trên tay màn hình bảo vệ mắt BenQ EW2770QZ giá 10,3 triệu

EBenQ là thương hiệu Đài Loan khá quen thuộc với người dùng Việt Nam, và dòng màn hình bảo vệ mắt EW là một trong những sản phẩm phổ biến nhất.