Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách làm cá nướng ngon tuyệt bằng nồi chiên không dầu

Đây là công thức nướng cá bằng nồi chiên không dầu dễ nhất và ngon nhất với rất ít gia vị cơ bản. Các chị em nội trợ có thể làm ngay một món ăn siêu ngon cho gia đình với công thức này.

Cách khắc phục lỗi lag trên iOS 11

Bạn đã tải phiên bản iOS 11 và nhận thấy rằng thiết bị của bạn bắt đầu bị lag khi sử dụng nó. Không chỉ có bạn gặp phải vấn đề như vậy, đặc biệt là trên các thiết bị iDevices thế hệ cũ. Dưới đây cách khắc phục lỗi lag

Nếu không thích trình duyệt mặc định Edge trong Windows 11, bạn có thể thay đổi nó

Khi truy cập Internet lần đầu trên Windows 11 ở một trình duyệt khác không phải là Edge, bạn sẽ được hỏi là có muốn thay đổi trình duyệt này thành mặc định hay không. Để đơn giản hóa quá trình thay đổi này, bạn có thể

Cách ngăn video tự động phát trong Microsoft Edge

Khi duyệt web với Microsoft Edge trên Windows 11, các tệp media nhúng trong các trang web sẽ tự động phát. Nhưng nếu không thích tính năng này, bạn có thể giới hạn hoặc tắt hoàn toàn nếu muốn.

Sự khác biệt giữa mật khẩu mạnh và yếu

Tạo mật khẩu từ càng nhiều ký tự ngẫu nhiên càng tốt. Tại sao vậy? Bởi vì nếu mật khẩu được tạo theo một mẫu số hay bàn phím thì tin tặc rất dễ đoán ra bằng công cụ phá mật khẩu dựa trên từ điển.

ĐÁNH GIÁ NHANH

Toyota Vios 1.5G 2019: Chiếc xe tối ưu cho những người thích bền bỉ, rộng rãi, ít hỏng vặt

Tại một thị trường không quá lớn như Việt Nam, việc một dòng xe đạt cột mốc doanh số 100.000 đơn vị là tương đối hiếm, và bất kể dòng xe nào làm được điều này thì đều xứng đáng được tôn

So sánh AirPods 2 và AirPods 3: Nâng cấp mới có làm nên chuyện?

Có thể nói, AirPods 3 được Apple trang bị nhiều tính năng mới hấp dẫn, đáp ứng tốt mọi nhu cầu của người dùng so với AirPods 2 trước đó.

Đánh giá nhanh MX6: Thiết kế đẹp mắt, cấu hình mạnh mẽ, pin 3.060 mAh sạc nhanh

Meizu MX6 thiết kế đẹp mắt, cùng cấu hình phần cứng mạnh mẽ, Helio X20, RAM 4GB, bộ nhớ trong 32GB. Bộ đôi camera trước sau lần lượt là 5MP và 12MP