Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Mách bạn mẹo thay đổi tên người dùng TikTok

Nếu bạn không muốn sử dụng tên người dùng TikTok hiện tại của mình, bạn có thể thay đổi thành tên bất kỳ trên ứng dụng.

Quên mật khẩu iPhone, phải làm sao?

Thường thì rất khó có thể quên 4 số mật mã (passcode) mở iPhone nhưng không có nghĩa là nó không xảy ra. Nếu bạn quên hoặc nhập sai passcode 6 lần trên iPhone hoặc iPad, thiết bị của bạn sẽ hiện thông báo 'bị vô hiệu

Cách kích hoạt giao diện trình duyệt Chrome mới trên iOS

Bằng cách kích hoạt giao diện mới của trình duyệt Chrome trên iOS, người dùng sẽ có được một giao diện mới đẹp mắt, hiện đại và dễ dàng thao tác hơn khi so với giao diện cũ. Bên cạnh đó, nhờ giao diện mới mà người dùng

Hướng dẫn sử dụng tính năng gửi email tự hủy với Gmail

Bên cạnh giao diện cập nhật mới thì người dùng sẽ được bổ sung thêm một số tính năng tiện lợi phục vụ cho việc gửi thư, tuy nhiên thì có vẻ sự bổ sung này chưa được đồng nhất khi mà ở lần trải nghiệm đầu tiên trên giao

Khóa màn hình máy tính, khóa Desktop Windows 10, 8.1, 7 chỉ bằng một click

Khóa màn hình máy tính từ lâu đã trở thành thao tác khá quen thuộc với nhiều người, từ giao diện đang làm việc, chúng ta có thể khóa màn hình và đứng lên để tránh người khác nhìn thấy giao diện làm việc. Vậy làm thế

ĐÁNH GIÁ NHANH

5 lý do nên mua iPhone 13 mini, đáng chú ý nhất là lý do số 3

Tuy không phải phiên bản cao cấp nhất nhưng iPhone 13 mini vẫn là lựa chọn tuyệt vời trong dịp cuối năm 2021. Có nhiều tính năng thú vị trên phiên bản mini này và đó cũng là những lý do nên mua iPhone 13 mini. Quay

Đánh giá chi tiết pin Samsung Galaxy C9 Pro - gần 22 tiếng sử dụng

Qua thử nghiệm thực tế, C9 Pro cho thời gian sử dụng hỗn hợp 21 tiếng 45 phút, onscreen được hơn 8 tiếng rưỡi và xem phim liên tục được gần 20 tiếng.