Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn khôi phục bài viết ẩn trên Facebook Timeline

Nếu lỡ tay ẩn (hide) bài viết trên 'tường' Facebook, bạn có thể khôi phục dễ dàng theo hướng dẫn dưới đây.

Cách cài đặt YouTube tự động phát lặp lại video vừa xem

Bài viết hướng dẫn bạn cách cài đặt YouTube sao cho video tự động phát lại sau khi đã “chạy” hết thời gian phát của nó mà không cần phải động tay vào chuột như thông thường hay cài thêm tiện ích, phần mềm nào khác.

Cách đặt và đổi mật khẩu trên Windows 7 nhanh chóng, tiện lợi

Hiện giờ có nhiều phần mềm của các nhà sản xuất cũng cho phép người sử dụng đặt mật khẩu để bảo vệ dữ liệu, nhưng đơn giản và nhanh nhất vẫn là đặt mật khẩu mặc định trên máy tính.

Đây là cách xuất ảnh trên Google Photos dễ nhất hiện nay

Google Photos cho phép người dùng lưu trữ trực tuyến ảnh và video. Tuy nhiên, bất cứ dịch vụ nào cũng có những lúc xảy ra bất trắc. Chính vì vậy mà bạn nên sao lưu dữ liệu định kỳ. Và dưới đây là cách xuất ảnh trên

Cách tắt xác minh hai bước trên iPhone

Nếu tính năng xác minh hai bước trên iPhone gây nhiều phiền phức cho bạn, bạn cũng có thể tắt tính năng này rất dễ dàng.

ĐÁNH GIÁ NHANH

Đánh giá Samsung Galaxy Tab A7: màn hình siêu rộng, “bom tấn giải trí” đáng mua trong phân khúc

Samsung Galaxy Tab A7 là chiếc máy tính bảng vừa được Samsung cho ra mắt vừa qua, máy nổi bật với thiết kế cao cấp & sang trọng, màn hình lớn siêu nét và cấu hình mạnh không kém gì những chiếc máy tính bảng đang

So sánh Redmi Watch 2 và Redmi Watch: Đánh giá sự khác biệt giữa hai thế hệ

Mới đây, Xiaomi đã khiến dân tình chao đảo khi cho ra mắt chiếc đồng hồ thông minh Redmi Watch 2. Có thể thấy, đây là phiên bản kế nhiệm của Redmi Watch đã được ra mắt năm 2020. Vậy, so với phiên bản trước thì Redmi

Đánh giá OPPO A55: Camera cảm biến 50MP, Pin 5000 mAh và phần cứng với Helio G35

Mới đây, OPPO vừa ra mắt mẫu điện thoại tầm trung OPPO A55 với giá 4.990.000 đồng. Không chỉ thừa hưởng các đặc điểm nổi bật của thế hệ trước OPPO A54 mà chiếc smartphone này còn được trang bị mạnh mẽ về ngoại hình và