Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn sửa lỗi không cài được VMware Tools

Bạn cài máy ảo thành công, nhưng không thể thực hiện thao tác kéo và thả file giữa máy thật vào máy ảo như trước nữa, bạn không thể fullscreen máy ảo... vì sao vậy? Thực ra rất đơn giản, lý do là VMware Workstation sử

Luyện tập đánh máy với Mario Teaches Typing

Trong mỗi cách thức học và bài luyện Mario Teaches Typing sẽ giới thiệu những cách chơi riêng cho bạn, như đếm thời gian gõ, số kỹ tự đã được gõ và số ký tự gõ sai.

Cách sửa lỗi “You do not have sufficient access to uninstall”, lỗi gỡ bỏ phần mềm

Đã bao giờ khi gỡ bỏ phần mềm, ứng dụng bất kỳ trên máy tính Windows, bạn nhận được thông báo lỗi “You do not have sufficient access to uninstall”. Nếu có thì bạn đã tìm đúng chìa khóa rồi đó. Dưới đây là 4 cách sửa

Chia sẻ một số công cụ miễn phí, hỗ trợ tìm và xóa file trùng lặp dành cho máy tính Windows

Đối với người dùng Windows, việc bị trùng lặp tập tin trong quá trình sử dụng là không thể tránh khỏi. Mặc dù điều đó không làm ảnh hưởng nhiều đến hệ điều hành, nhưng nếu rất dễ gây ra tình trạng thiếu hụt bộ nhớ trên

5 cách giúp smartphone kết nối 4G nhanh

Trong nhiều trường hợp, mạng 4G sẽ là cứu cánh của bạn khi kết nối Wifi bị ngắt hay không đảm bảo. Để có thể sử dụng hiệu quả chúng, bạn hãy tham khảo một vài cách giúp smartphone kết nối 4G nhanh và đơn giản dưới đây.

ĐÁNH GIÁ NHANH

Đánh giá pin di dộng Anker PowerCore+ 26800 PD: hơn 4 tiếng để sạc đầy

Thử nghiệm cho thấy dung lượng thật của pin đạt khoảng 60% so với công bố nhưng vẫn có thể còn chênh lệch trong quá trình sử dụng thực tế.

Đánh giá thiết kế Galaxy A8(2018): đâu là điểm đáng khen, đâu là điểm chưa thuyết phục

Cảm giác lần đầu cầm Galaxy A8 (2018) khiến mình khá ngạc nhiên về sự nhỏ gọn của nó. Nó y chang cảm xúc lần đầu mình cầm chiếc Galaxy S8, nơi mà phong trào màn hình vô cực, màn hình tràn viền bắt đầu khơi mào.

Đánh giá loa không dây Cambridge Audio G5: Đẹp, hay, đa năng

Thiết kế Sự cao cấp của Cambridge Audio G5 thể hiện ngay ở thiết kế của nó. Bề mặt của G5 được phủ hai...