Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách resize, thay đổi kích cỡ hàng loạt ảnh với Light Image Resizer

Nếu album ảnh của bạn có kích cỡ lớn, có thể sẽ phải mất một khoảng thời gian dài để bạn upload được lên mạng xã hội này, cách đơn giản nhất là resize ảnh được chụp, thay đổi kích cỡ ảnh sẽ làm giảm bớt dung lượng cũng

Thay đổi giao diện màn hình chính với Rainmeter

Một trong những phần mềm phổ biến để thay thế những widget cũ của windows là Rainmeter, bạn có thể tùy chỉnh giao diện màn hình chính máy tính của bạn với những bộ skin cực đẹp và độc, ưu thế của Rainmeter là dung

Hướng dẫn xóa file gốc sau khi nén bằng winRAR

Thường thì với quá trình nén file, sau khi thực hiện xong, chúng ta sẽ thu được một file mới và đồng thời các file cũ cũng vẫn sẽ được giữ nguyên. Thực ra điều này là không cần thiết, bởi trong file nén các bạn vừa tạo

Cách sửa Zalo lỗi 600, 602, 606, 647

Bạn gặp thông báo lỗi Zalo 600, 602, 606, 647 trong quá trình sử dụng và không sao xử lý được mặc dù đã làm nhiều mọi cách. Bài viết dưới đây là giải pháp mà TCN dành cho bạn để thực hiện sửa Zalo lỗi 600, 602, 606,

Cách reset mật khẩu, password Snapchat trên điện thoại và máy tính

Như các bạn đã biết, Snapchat hiện nay là 1 trong những ứng dụng chat, nhắn tin, trò chuyện trực tuyến phổ biến nhất trên thế giới, là 1 đối thủ nặng ký của mạng xã hội Facebook. Và trong bài viết dưới đây, hãy cùng

ĐÁNH GIÁ NHANH

[Review] iPad Pro 10.5 + Smart Keyboard đã làm mình muốn rời xa MacBook Pro

Trong bài này mình sẽ đánh giá chung hai món: iPad Pro 10.5 và bàn phím Apple Smart Keyboard. Hai món này hợp lại sẽ giải quyết được hầu hết các nhu cầu cơ bản của bạn trên máy tính.

Review camera Huawei nova 2i: chi tiết ảnh và tổng thể màu sắc tốt, lấy nét nhanh, bokeh đẹp

Huawei nova 2i là chiếc điện thoại nằm trong phân khúc tầm trung của Huawei, mới vừa ra mắt tại thị trường Việt Nam gần đây với mức giá rất tốt, còn tốt hơn cả giá tại thị trường Thái Lan hiện tại. Dòng sản phẩm này

Trải nghiệm, đánh giá Yamaha YZF-R1 2016 tại Sài Gòn

Độ nhạy bướm ga linh hoạt, khả năng tăng tốc mạnh mẽ và mức độ bứt phá cực kì phấn khích cùng âm thanh mê hoặc là những gì mà superbike Yamaha R1 2016 mang lại cho người cầm lái.