Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Khôi phục dữ liệu trên iPhone

Người dùng iPhone khi đồng bộ dữ liệu giữa thiết bị và máy tính thông qua iTunes có thể vô tình bị xóa tất cả các dữ liệu được lưu trữ trên thiết bị của bạn, trong đó bao gồm cả các dữ liệu quan trọng được. Tuy nhiên,

Cách chuyển tin nhắn trên Zalo thành nhật ký cực kỳ tiện lợi cho bạn

Có những lúc bạn muốn chuyển tin nhắn nào đó trên Zalo thành nhật ký của mình mà bạn lại không biết thì hãy xem ngay cách chuyển tiếp tin nhắn trên Zalo thành nhật ký nhé!

Hướng dẫn đăng ký bản quyền video trên Youtube

Video của bạn sau khi đăng ký bản quyền với Youtube sẽ phải chờ đợi việc kiểm duyệt để xác minh quyền sở hữu video. Nếu video đăng ký video thành công Youtube sẽ tuyệt đối bảo vệ bản quyền, các video với nội dung tương

Bạn cần để lại bao nhiêu dung lượng lưu trữ trống trên iPhone là đủ?

Thật dễ dàng để lấp đầy bộ nhớ của iPhone với các ứng dụng, hình ảnh và video, nhưng không bởi vì thế mà bạn nên làm vậy. Sử dụng đến ngưỡng nào thì được coi là đầy bộ nhớ?

System Info - Thêm thông tin trong mục giới thiệu, sao lưu SHSH blobs ngay trên máy

Apple đã cung cấp cho người dùng một số thông tin về iPhone, iPad trong mục giới thiệu như tên, số hiệu máy, phiên bản hệ điều hành, dung lượng, imei v.v...

ĐÁNH GIÁ NHANH

Thời lượng pin Mate 20 Pro: Đủ để đồng hành cùng người dùng xuyên suốt cả ngày

Thử thách đầu tiên, mình sẽ xem Youtube độ phân giải cao liên tục, để xem tốc độ tiêu thụ pin trên Huawei Mate 20 Pro như thế nào? Chiếc điện thoại này mất 1 giờ 10 phút để tiêu thụ 10% pin (từ 100% xuống 90%).

Đánh giá nhanh Sony XA2 Ultra mới xem có gì "ngon"

Cũng như bất kỳ sản phẩm nào của Sony, Xperia XA2 Ultra vẫn không ngoại lệ khi giữ cho mình vẻ đẹp'truyền thống' trong phong cách thiết kế.

So sánh AirPods 3 và AirPods Pro: Đâu là sản phẩm đáng mua hơn cả?

AirPods 3 và AirPods Pro đều là những mẫu tai nghe cao cấp được trang bị nhiều tính năng thông minh, hấp dẫn của Apple. Vậy khi đặt lên bàn cân so sánh AirPods 3 và AirPods Pro thì đâu là sản phẩm đáng mua hơn cả? Hãy