Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Hướng dẫn chuyển đổi giao diện Steam thành tiếng việt

Việc làm này cho thấy rằng Steam bắt đầu quan tâm hơn đến cộng đồng game thủ Việt Nam và giúp các bạn game thủ có thể tiếp cận dễ dàng hơn với hệ thống bán hàng của Steam.

Update iOS 11.2 Beta 3: có thể tắt bật Bluetooth và Wifi trong Control Center lâu hơn

Bản cập nhật iOS 11.2 Beta 3 (15C5107a) cho các thiết bị có dung lượng tải từ 140 – 250MB tùy theo đời máy.

Cách tạo file bat giúp xử lý lỗi 100% Disk Usage trên Windows 10

Bạn đang sử dụng Windows 10 và thường xuyên rơi vào tình trạng 100% Disk Usage? Hôm nay, TCN sẽ hướng dẫn các bạn cách tạo file bat giúp xử lý lỗi 100% Disk Usage trên Windows 10.

Những mẹo xóa vết xước màn hình điện thoại đơn giản

Thật vậy, chẳng cần đến những thủ thuật xóa bỏ vết xước cao siêu cũng như đòi hỏi công cụ chuyên nghiệp, người dùng có thể tự mình xóa bỏ vết xước màn hình điện thoại hay laptop bằng những mẹo vặt vô cùng đơn giản như

Hướng dẫn cách chặn mua ứng dụng trên Apple Store

App Store là kho ứng dụng dành riêng cho các thiết bị sử dụng hệ điều hành iOS, tại đây chúng ta có thể tìm kiếm tất cả những gì mình cần, dù chúng là miễn phí hay phải mất phí để có thể sử dụng.

ĐÁNH GIÁ NHANH

Đánh giá Galaxy J2 Prime - smartphone giá rẻ có hiệu năng tốt nhất

Samsung Galaxy J2 prime là chiếc điện thoại chuẩn bị được bán ra tại thị trường Việt Nam, máy nằm trong phân khúc giá rẻ, tuy nhiên hiệu năng Galaxy J2 Prime lại được đánh giá khá tốt so với mức giá.

Trên tay Diesel On Full Guard: smartwatch cho dân đeo đồng hồ đích thực

Chỉ cần 350usd là anh em có một chiếc đồng hồ thông minh trong thân hình một chiếc đồng hồ thời trang thực sự như chiếc Diesel On Full Guard này. Thiết kế hầm hố, hoàn thiện tốt, dây da đẹp... và dĩ nhiên với Android

Đánh giá nhanh Samsung Galaxy A3 2016

Không chỉ sở hữu ngoại hình đẹp mắt nhờ sự phối kết hợp từ kim loại và kính, Samsung Galaxy A3 2016 còn cung cấp hiệu năng hoạt động tốt với giá thành phải chăng.