Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Top phần mềm luyện gõ bàn phím Windows

Máy tính, smartphone, máy tính bảng hay các thiết bị công nghệ điện tử khác đang là một phần không thể thiếu trong cuộc sống hiện đại ngày nay. Có không ít những gia đình còn hướng cho con em mình làm quen với những

Các lỗi kèm theo cách khắc phục trong Windows 10 Insider Preview build 17112

Windows 10 (Redstone 4) Insider Preview build 17112 đã được phát hành qua kênh Insider Fast nhằm nối tiếp những cải tiến cho hệ điều hành Windows 10 kể từ build 17110.

Những nguyên tắc không thể quên khi sử dụng pin smartphone

Những nguyên tắc sử dụng pin ngỡ như vô cùng đơn giản nhưng hầu hết người dùng đều bỏ qua, điều này đã vô tình khiến pin trên chiếc smartphone trở nên nhanh hỏng hơn. Và sau đây là danh sách các nguyên tắc bạn cần tuân

IDM full crack 2017 – giải pháp download cực mạnh

Không cần phải nói nhiều về khả năng download của IDM Full Crack 2017, có thể kể đến: Tương thích với hầu hết tất cả các trình duyệt web hiện nay, IDM full có khả năng tải về chỉ với 1 click...

Mang giao diện đẹp như mơ của Macbook lên smartphone của bạn

Nếu bạn đã quá nhàm chán với giao diện mặc định trên smartphone thì hôm nay, mình sẽ giới thiệu cho bạn một giao diện mới cực kì mới mẻ và thú vị...

ĐÁNH GIÁ NHANH

Đánh giá Xiaomi Pad 6 xách tay: Sự lựa chọn tuyệt vời cho tablet Android phân khúc 7 triệu đồng

Trong sự kiện tổ chức vào ngày 18/4 theo giờ Việt Nam, Xiaomi đã giới thiệu mẫu máy tính bảng mới nhất của họ là Xiaomi Pad 6, song song với sản phẩm Xiaomi 13 Ultra. Với giá khoảng 7 triệu đồng cho phiên bản xách tay,

Đánh giá camera Huawei Nova 3e: Khả năng chụp hình ấn tượng với giá 7 triệu đồng

Điểm qua thông số phần cứng camera của máy. Nova 3e được trang bị camera kép phía sau với một cảm biến 16MP khẩu độ f/2.2 và một camera 2MP phục vụ cho việc chụp chân dung xóa phông chất lượng hơn. Trong khi đó ở phía

Với giá 6,6 triệu đồng, Nokia 6.1 Plus có thực sự đáng mua không?

Nokia của HMD Global đã bắt đầu năm 2018 với Nokia 7 Plus thực sự rất ấn tượng. Điện thoại trông tuyệt đẹp, có một chiếc máy ảnh tuyệt vời và hoạt động cực nhanh với Android One. Nhưng Nokia 6.1 thì lại ngược lại, nó