Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Cách nhận biết iPhone đã qua sửa chữa rất đơn giản mà bạn nên biết

Có nhiều lỗi trên iPhone khi sử dụng lâu dài mới phát sinh. Vì thế trong bài viết này mình hướng dẫn các bạn cách nhận biết iPhone đã qua sửa chữa rất đơn giản.

Hướng dẫn sắp xếp biểu tượng trên iPhone theo ý thích cá nhân không cần jailbreak

Với iPhone thì bạn sẽ phải jailbreak thiết bị để có thể sắp xếp vị trí các icon trên màn hình chính theo ý thích. Giờ đây, TECHRUM xin chia sẻ cách thực hiện đơn giản hơn mà không cần phải jailbreak.

Tổng quan về Office Deployment Tool

Office Deployment Tool bao gồm hai file: setup.exe và configuration.xml. Để làm việc với công cụ này, bạn có thể chỉnh sửa file cấu hình để xác định tùy chọn bạn muốn, rồi chạy setup.exe từ dòng lệnh. Ví dụ, bạn có thể

Hướng dẫn cách thiết lập đo tốc độ mạng trên Speedtest

Speedtest là dịch vụ trực tuyến giúp người dùng đo tốc độ mạng internet của nhà mạng mình đang dùng như Viettel, FPT hay VNPT

Đây là 7 cách khắc phục lỗi Instagram không hoạt động

Instagram được biết đến là một nền tảng mạng xã hội phổ biến trên toàn thế giới. Người dùng Instagram có thể chia sẻ những khoảnh khắc đời thường, nhắn tin hay thậm chí kinh doanh trên nền tảng này.

ĐÁNH GIÁ NHANH

Điểm danh các ứng dụng tra cứu điểm thi 2023, phụ huynh & học sinh không được bỏ qua

Còn chưa đầy 2 tháng nữa, các bạn học sinh trên toàn quốc sẽ chính thức bước vào kỳ thi chuyển cấp lên 10 và THPT Quốc gia 2023. Hiểu được điều này, Trangcongnghe.vn đã tổng hợp các ứng dụng tra cứu điểm thi cực hay

Mở hộp và đánh giá nhanh Oppo A39: máy đẹp, gọn nhẹ, độ hoàn thiện cao

Với ngoại hình tương tự như F1s cùng mức giá dễ chịu là 5 triệu đồng, Oppo A39 sớm trở thành sản phẩm được săn đón nhất trong mùa mua sắm cuối năm.