Webuild: Progress in the construction of the new breakwater dam in Genoa

MILAN, Italy, Aug. 01, 2023 (GLOBE NEWSWIRE) -- At the construction site of the new breakwater dam in Genoa, underwater unexploded ordnance clearance operations have begun at depths of up to 50 meters. Webuild, the first company in Italy to do so, is using a special operational method that involves employing saturation divers. The operations will continue for 60 consecutive days, during which the divers will take turns being brought to saturation and then descend and ascend from the seafloor.

The new breakwater dam in Genoa is being constructed by the consortium PERGENOVA BREAKWATER, led by Webuild in collaboration with Fincantieri Infrastructure Opere Marittime, Fincosit, and Sidra. Rina is entrusted with the project management consulting activities. The project was commissioned by the Western Ligurian Sea Port Authority. For the construction of the dam, which will also benefit from the NRRP (National Recovery and Resilience Plan) funds, it is estimated that 1,000 people, including direct and third-party personnel, will be employed.

The clearance operations, carried out in collaboration with Drafinsub, involve 8 saturation divers who are taken to the depths in groups of 2 using a diving bell. The divers take turns spending 4 hours each underwater before being replaced by another pair. The operations are coordinated from a pontoon on the surface, where a saturation system has been set up, along with a support operation system, a 1,200 KW power generation station, and accommodation for the 32 technicians who will live and work onboard the vessel throughout the construction phase, ensuring the operations are carried out in complete safety. A control room allows for the monitoring of all parameters of the diving bell and hyperbaric chambers. The operations will continue, 7 days a week and 24 hours a day.

In addition to the unexploded ordnance clearance, the construction site of the new breakwater dam is also continuing with the consolidation operations of the seafloor that began on July 7. This has already resulted in the completion of approximately 220 out of the 70,000 gravel columns that will provide stability to the foundation on which the future defense structure will rest. The gravel-laying activities on the seafloor are also ongoing, with approximately 200,000 tons of material already placed, utilizing a vessel with a capacity of 3,600 tons and two smaller pontoons with a total capacity of about 700 tons. On average, these vessels transport 3,000 tons of gravel per day and have completed over 90 round trips so far, departing from Piombino and Genoa.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/385f480c-1775-477d-a51c-8645833afe17

The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.

 


Webuild: Progress in the construction of the new breakwater dam in Genoa

TIN LIÊN QUAN

Fix-It Right Plumbing Hosts Grand Opening of Adelaide

Breakwater, March 15, 2023 (GLOBE NEWSWIRE) -- Breakwater, Victoria - Adelaide, South Australia – After a year in the making, Fix-It Right Plumbing is...

Construction of the fifth stage of the Lahekalda

AS Merko Ehitus Eesti, part of AS Merko Ehitus group, has decided to proceed with the construction of the above grade volumes of the Lahekalda residential...

Ecobot Earns 2022 EBJ Business Achievement Award

ASHEVILLE, N.C., Feb. 16, 2023 (GLOBE NEWSWIRE) -- Ecobot, the premier digital solution for mandatory pre-construction assessments, has received a 2022...

THỦ THUẬT HAY

Tìm hiểu bản nâng cấp MacOS Mojave 10.14 có gì mới ?

Apple lần đầu tiên ra mắt phiên bản macOS ‘Mojave’ mới nhất tại hội nghị WWDC hồi tháng 6. Tuy nhiên đến tháng 9 tức là sau 3 tháng, người dùng máy tính Mac mới có thể tải về Mojave bản chính thức. Đây là bản cập nhật

Hướng dẫn sửa lỗi SSL khi đăng nhập Facebook, Gmail, Youtube

Để đảm bảo an toàn cao thì giao thức bảo mật này sẽ có những cảnh báo khi bạn truy cập từ các thiết bị hoặc trình duyệt được cho là không an toàn. Ví dụ như báo lỗi SSL (lỗi chứng chỉ không hợp lệ) do đặt thời gian

Hướng dẫn xem trực tiếp bóng đá Sea Games 29 qua mạng

SEA Games 29 đã chính thức khởi tranh lúc 15h00 chiều ngày 14/8, toàn bộ các trận đấu sẽ tường thuật trực tiếp trên kênh VTV6 và VTV6 HD.

Hướng dẫn sử dụng chế độ Night Sight của Google cho điện thoại Pixel

Hiện tại, Night Sight vẫn chưa chính thức xuất hiện. Google cho biết sẽ triển khai tính năng mới cho Pixel 3 và các thiết bị Pixel khác vào tháng sau. Tuy nhiên, mới đây, một thành viên cấp cao của trang XDA có

File DLL là gì?Tại sao đôi khi máy tính thông báo file DLL đang bị thiếu?

Thi thoảng trong khi sử dụng máy tính, bạn lại nhận được một thông báo lỗi có nội dung là Windows không thể tìm thấy một tập tin DLL xác định.

ĐÁNH GIÁ NHANH

Đánh giá Oppo F9: Ngoài camera selfie thì còn gì nữa?

OPPO F9 là chiếc smartphone tầm trung mới nhất vừa được giới thiệu với nhiều điểm nhấn hấp dẫn. Vậy ngoài danh tiếng camera selfie thì sản phẩm...

Trên tay điện thoại Samsung Galaxy A32 5G : Phân khúc 5G giá rẻ

Samsung Galaxy A32 5G có thân máy được làm từ chất liệu nhựa cứng với bốn cạnh bo tròn nhẹ giống với các model thuộc dòng Galaxy A của Samsung. Chiếc máy có 4 tùy chọn màu sắc khác nhau là

Xe máy Kymco K-Pipe

Kymco K-Pipe là mẫu xe côn tay khá quen thuộc với người tiêu dùng Việt Nam sở hữu cho mình kiểu dáng đậm chất thể thao hướng theo giới trẻ mà dòng xe này được ưu chuộng để di chuyển trong phố cũng như các chuyến Tour