Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

MILAN, Italy, July 17, 2023 (GLOBE NEWSWIRE) -- In the 'underwater' construction site of the New Breakwater in Genoa, an important new phase of work is underway to consolidate the seabed. In the area identified as Test Area 1, the first gravel columns that will guarantee stability to the base on which the future barrier will rest have taken shape. The columns to be built are 70,000 and will run along the entire perimeter of the new dam. To date, approximately 100 columns have already been constructed. Within the first month, approximately 850 will be constructed, with the aim of completing them all within the next 17 months.

At the same time, the work of laying gravel on the seabed continues at full pace, where about 185,000 tonnes of material have already been laid, using a 3,600-tonne capacity ship and two smaller pontoons with a total capacity of about 700 tonnes, which carry an average of 3,000 tonnes of gravel per day and have already made a total of about 90 round trips, starting from Piombino and Genoa.

The New Breakwater is being built by the PERGENOVA BREAKWATER consortium, led by Webuild in cooperation with Fincantieri Infrastructure Opere Marittime, Fincosit and Sidra, while Rina is in charge of project management consulting. The work was commissioned by the Western Ligurian Sea Port System Authority. For the construction of the dam, which will also benefit from PNRR funding, it is estimated that one thousand people will be employed, including direct personnel and third parties.

The gravel columns will be built using an innovative technique known as the “Wet Top Feed – Blanket Method”. The technique involves the use of a vibrating probe, the vibroflot, a kind of needle between 17 and 21 metres long. The probe, attached to 40-metre-high cranes positioned on floating platforms, the pontoons, is brought to the seabed on which a layer of gravel thick enough to accommodate columns over 13 metres high has previously been placed. By vibrating and using combined water and air jets, the probe penetrates the ground and creates a tubular-shaped space into which the surrounding gravel material gradually slides. As the gravel slides, the future column takes shape and is progressively compacted.

The New Breakwater, the largest intervention ever carried out for the enhancement of Italy’s ports, is a barrier whose main task will be to protect the port of Genoa from wave motion. A unique work of its kind in engineering terms, in its final configuration it will be 6,200 metres long and will replace the existing breakwater, but will be positioned at a distance from the quay that will allow access to the port even for modern ships defined as 'Ultra large', which today suffer from limitations due to the reduced room for manoeuvre.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6e388d27-c215-4398-8371-2d7a9d0c17b7. The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.


Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

THỦ THUẬT HAY

Cách tự động xóa tin nhắn Zalo trên điện thoại và máy tính cực nhanh

Cách tự động xóa tin nhắn Zalo trên điện thoại và máy tính này sẽ giúp bạn tự động xóa các tin nhắn riêng tư theo thời gian mà bạn thiết lập cho cuộc hội thoại

Hướng dẫn quét mống mắt hiệu quả trên Galaxy S8

Quét mống mắt là phương thức bảo mật hệ thống mà Galaxy S8 và Galaxy S8 Plus sử dụng, ngoài hình thức bảo mật vân tay và mật khẩu.

Hướng dẫn lưu toàn bộ trang web về iPhone theo định dạng PDF

Thủ thuật này thực hiện hoàn toàn trên hệ điều hành iOS mà không cần đến ứng dụng bên thứ 3 nào. Kể từ iOS 11, Apple đã cung cấp cho hệ điều hành iOS ứng dụng quản lý tệp có tên “Files”. Nhờ ứng dụng này mà chúng ta có

Ebay bị hack và người dùng nên thay đổi mật khẩu ngay lập tức

Cơ sở dữ liệu mật khẩu của Ebay đã bị xâm nhập. Điều này có nghĩa người dùng Ebay nên thay đổi mật khẩu càng sớm càng tốt. Trong khi đó, công ty này sẽ gửi email đến người dùng vào ngày hôm nay.

Những mẹo giúp bạn sử dụng TeamViewer hiệu quả và mượt mà hơn

Nếu bạn muốn thực sự sử dụng thiết bị bạn đang kết nối tới như máy tính ngay trước mặt mình thì bạn cần điều chỉnh cài đặt toàn màn hình. Để làm được điều này, sau khi kết nối, trên thanh công cụ của TeamViewer ở phía

ĐÁNH GIÁ NHANH

Đánh giá nhanh camera Vivo Y81: Chất lượng camera đủ để sử dụng

Vivo Y81 được trang bị camera sau 13MP khẩu độ f/2.2, camera trước 5MP khẩu độ cũng là f/2.2. Camera trước có khả năng chụp selfie xóa phông, làm đẹp khuôn mặt bằng AI, cả camera trước và sau đều có tính năng HDR.

Đánh giá loa di động B&O BeoPlay A1: Nhỏ gọn nhưng đầy sức mạnh

ĐÁNH GIÁ CHUNG B&O BeoPlay A1 là một mẫu loa di động hiếm hoi trên thị trường hiện nay đáp...