Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

MILAN, Italy, July 17, 2023 (GLOBE NEWSWIRE) -- In the 'underwater' construction site of the New Breakwater in Genoa, an important new phase of work is underway to consolidate the seabed. In the area identified as Test Area 1, the first gravel columns that will guarantee stability to the base on which the future barrier will rest have taken shape. The columns to be built are 70,000 and will run along the entire perimeter of the new dam. To date, approximately 100 columns have already been constructed. Within the first month, approximately 850 will be constructed, with the aim of completing them all within the next 17 months.

At the same time, the work of laying gravel on the seabed continues at full pace, where about 185,000 tonnes of material have already been laid, using a 3,600-tonne capacity ship and two smaller pontoons with a total capacity of about 700 tonnes, which carry an average of 3,000 tonnes of gravel per day and have already made a total of about 90 round trips, starting from Piombino and Genoa.

The New Breakwater is being built by the PERGENOVA BREAKWATER consortium, led by Webuild in cooperation with Fincantieri Infrastructure Opere Marittime, Fincosit and Sidra, while Rina is in charge of project management consulting. The work was commissioned by the Western Ligurian Sea Port System Authority. For the construction of the dam, which will also benefit from PNRR funding, it is estimated that one thousand people will be employed, including direct personnel and third parties.

The gravel columns will be built using an innovative technique known as the “Wet Top Feed – Blanket Method”. The technique involves the use of a vibrating probe, the vibroflot, a kind of needle between 17 and 21 metres long. The probe, attached to 40-metre-high cranes positioned on floating platforms, the pontoons, is brought to the seabed on which a layer of gravel thick enough to accommodate columns over 13 metres high has previously been placed. By vibrating and using combined water and air jets, the probe penetrates the ground and creates a tubular-shaped space into which the surrounding gravel material gradually slides. As the gravel slides, the future column takes shape and is progressively compacted.

The New Breakwater, the largest intervention ever carried out for the enhancement of Italy’s ports, is a barrier whose main task will be to protect the port of Genoa from wave motion. A unique work of its kind in engineering terms, in its final configuration it will be 6,200 metres long and will replace the existing breakwater, but will be positioned at a distance from the quay that will allow access to the port even for modern ships defined as 'Ultra large', which today suffer from limitations due to the reduced room for manoeuvre.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6e388d27-c215-4398-8371-2d7a9d0c17b7. The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.


Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

THỦ THUẬT HAY

Phải làm sao để khắc phục GPU tăng trên Windows? [Chi tiết A-Z]

Nếu GPU của bạn đang hoạt động ở mức tăng cao bất thường ngay cả đang chạy các tiến trình sử dụng ít tài nguyên và game mà bạn chơi bị lag, giật hoặc treo bất thường thì có thể do các vấn đề phần mềm hoặc phần cứng.

Hướng dẫn tắt tính năng tải lại tab trên Google Chrome

Đó chính là tính năng Automatic Tab Discarding, cho phép tự động load trang sau một thời gian nhất định. Vậy tốt nhất hãy chặn Chrome tự động tải lại tab cũ, sẽ giúp cho máy tính chạy nhanh hơn, giảm thời gian lướt web

Hưỡng dẫn cài đặt Ajaxplorer giải nén trên Zpanel và nhiều hơn nữa

Thường chúng ta khi cài đặt Zpanel xong thì mặc định phần quản trị đó không được cài sẵn quản lý thư mục như zip, unzip, copy, paste...Sau đây TCN sẽ hưỡng dẫn các bạn setup module có những chức năng tối thiểu đó.

Cách kết nối các thiết bị Roku với TV qua cổng HDMI

Thiết bị phát Roku có thể biến bất kỳ TV nào thành TV thông minh, cho phép bạn truy cập nhiều dịch vụ trực tuyến khác nhau. Đa phần các thiết bị Roku được thiết kế để kết nối với TV qua cổng HDMI. Sau khi kết nối Roku

Cách ẩn thanh điều hướng OPPO để dùng thao tác vuốt chạm cực hấp dẫn

Việc ẩn thanh điều hướng trên OPPO sẽ mang đến những trải nghiệm mới với những thao tác cử chỉ vuốt chạm hấp dẫn hơn. Sau đây là cách ẩn thanh điều hướng OPPO...

ĐÁNH GIÁ NHANH

Router 4 râu Prolink PRC3801: Thiết bị ổn trong tầm giá 1 triệu đồng

Nếu như bạn là game thủ, yêu cầu đường truyền ổn định tốc độ cao thì hãy nói không với các router rẻ tiền được nhà mạng phát miễn phí. Thay vào...

Lần đầu lái thử Ford Kuga/Escape 2017 facelift

Đã đến lúc Ford Kuga (hay Escape, như cách gọi ở các châu lục khác) được nâng cấp giữa chu kỳ, lần nâng cấp này là một phần kế hoạch của hãng xe Mỹ nhằm củng cố dòng SUV của mình tại châu Âu.

Đánh giá tai nghe QCY QY31: Thiết kế thể thao, mạnh mẽ, chất lượng ổn

Cũng giống như những chiếc tai nghe thể thao khác, QY31 cũng có phần quay đeo để móc vào vành tai người dùng. Điều này sẽ giúp các bạn trong khi vận động mạnh như chơi thể thao sẽ không bị rơi tai nghe ra bên ngoài.