Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

MILAN, Italy, July 17, 2023 (GLOBE NEWSWIRE) -- In the 'underwater' construction site of the New Breakwater in Genoa, an important new phase of work is underway to consolidate the seabed. In the area identified as Test Area 1, the first gravel columns that will guarantee stability to the base on which the future barrier will rest have taken shape. The columns to be built are 70,000 and will run along the entire perimeter of the new dam. To date, approximately 100 columns have already been constructed. Within the first month, approximately 850 will be constructed, with the aim of completing them all within the next 17 months.

At the same time, the work of laying gravel on the seabed continues at full pace, where about 185,000 tonnes of material have already been laid, using a 3,600-tonne capacity ship and two smaller pontoons with a total capacity of about 700 tonnes, which carry an average of 3,000 tonnes of gravel per day and have already made a total of about 90 round trips, starting from Piombino and Genoa.

The New Breakwater is being built by the PERGENOVA BREAKWATER consortium, led by Webuild in cooperation with Fincantieri Infrastructure Opere Marittime, Fincosit and Sidra, while Rina is in charge of project management consulting. The work was commissioned by the Western Ligurian Sea Port System Authority. For the construction of the dam, which will also benefit from PNRR funding, it is estimated that one thousand people will be employed, including direct personnel and third parties.

The gravel columns will be built using an innovative technique known as the “Wet Top Feed – Blanket Method”. The technique involves the use of a vibrating probe, the vibroflot, a kind of needle between 17 and 21 metres long. The probe, attached to 40-metre-high cranes positioned on floating platforms, the pontoons, is brought to the seabed on which a layer of gravel thick enough to accommodate columns over 13 metres high has previously been placed. By vibrating and using combined water and air jets, the probe penetrates the ground and creates a tubular-shaped space into which the surrounding gravel material gradually slides. As the gravel slides, the future column takes shape and is progressively compacted.

The New Breakwater, the largest intervention ever carried out for the enhancement of Italy’s ports, is a barrier whose main task will be to protect the port of Genoa from wave motion. A unique work of its kind in engineering terms, in its final configuration it will be 6,200 metres long and will replace the existing breakwater, but will be positioned at a distance from the quay that will allow access to the port even for modern ships defined as 'Ultra large', which today suffer from limitations due to the reduced room for manoeuvre.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6e388d27-c215-4398-8371-2d7a9d0c17b7. The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.


Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

THỦ THUẬT HAY

6 niềm tin sai lầm vẫn còn tồn tại nơi công sở

Nhân viên phải làm việc đủ 8 tiếng mỗi ngày hay cứ nhắc đến tạo động lực là phải sử dụng tiền... chính là hai trong số những suy nghĩ vô cùng 'lạc hậu' cần thay đổi!

Ứng dụng giúp bạn trông chừng và bảo vệ con cái

Lưu ý quan trọng cho người dùng là ứng dụng này chỉ hoạt động khi bạn đã có tài khoản Spyzie, và đăng nhập trên ứng dụng Spyzie được cài đặt trên thiết bị được giám sát (smartphone, tablet).

9 gói giao diện miễn phí đến từ Microsoft, mời các bạn tải về

Microsoft vừa phát hành 09 giao diện (theme) mới hoàn toàn miễn phí cho Windows 10 trên Microsoft Store. Nếu muốn thay giao diện và hình nền Windows 10 mới, hãy lựa chọn và tải về nhé.

Làm thế nào để tắt chế độ chạy ngầm của Chrome?

Nếu bạn cho rằng chỉ click vào biểu tượng Close của Chrome là trình duyệt này đã tắt hoàn toàn. Đôi khi Chrome chạy ngầm mà chúng ta không hề biết và điều này gây ra khá nhiều vấn đề khó

Cách kết nối điện thoại với Tivi, kết nối điện thoại iPhone, Android, Winphone với Tivi

Có rất nhiều cách giúp bạn kết nối điện thoại với Tivi bao gồm các hệ điều hành iPhone, Android và Winphone. Trong bài viết này chúng tôi sẽ hướng dẫn các bạn các cách đơn giản nhất để có thể kết nối điện thoại với

ĐÁNH GIÁ NHANH

Đánh giá nhanh Cân Xiaomi Smart Scale 2

Nói về Xiao thì có lẽ thương hiệu này đã quá nổi tiếng rồi. Đây là một Tập đoàn sản xuất hàng điện tử của Trung Quốc, là một trong những ông lớn trong ngành công nghệ, đã khẳng định tên tuổi của mình qua rất nhiều sản

Đánh giá nhanh Sony XA2 Ultra mới xem có gì "ngon"

Cũng như bất kỳ sản phẩm nào của Sony, Xperia XA2 Ultra vẫn không ngoại lệ khi giữ cho mình vẻ đẹp'truyền thống' trong phong cách thiết kế.