Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

MILAN, Italy, July 17, 2023 (GLOBE NEWSWIRE) -- In the 'underwater' construction site of the New Breakwater in Genoa, an important new phase of work is underway to consolidate the seabed. In the area identified as Test Area 1, the first gravel columns that will guarantee stability to the base on which the future barrier will rest have taken shape. The columns to be built are 70,000 and will run along the entire perimeter of the new dam. To date, approximately 100 columns have already been constructed. Within the first month, approximately 850 will be constructed, with the aim of completing them all within the next 17 months.

At the same time, the work of laying gravel on the seabed continues at full pace, where about 185,000 tonnes of material have already been laid, using a 3,600-tonne capacity ship and two smaller pontoons with a total capacity of about 700 tonnes, which carry an average of 3,000 tonnes of gravel per day and have already made a total of about 90 round trips, starting from Piombino and Genoa.

The New Breakwater is being built by the PERGENOVA BREAKWATER consortium, led by Webuild in cooperation with Fincantieri Infrastructure Opere Marittime, Fincosit and Sidra, while Rina is in charge of project management consulting. The work was commissioned by the Western Ligurian Sea Port System Authority. For the construction of the dam, which will also benefit from PNRR funding, it is estimated that one thousand people will be employed, including direct personnel and third parties.

The gravel columns will be built using an innovative technique known as the “Wet Top Feed – Blanket Method”. The technique involves the use of a vibrating probe, the vibroflot, a kind of needle between 17 and 21 metres long. The probe, attached to 40-metre-high cranes positioned on floating platforms, the pontoons, is brought to the seabed on which a layer of gravel thick enough to accommodate columns over 13 metres high has previously been placed. By vibrating and using combined water and air jets, the probe penetrates the ground and creates a tubular-shaped space into which the surrounding gravel material gradually slides. As the gravel slides, the future column takes shape and is progressively compacted.

The New Breakwater, the largest intervention ever carried out for the enhancement of Italy’s ports, is a barrier whose main task will be to protect the port of Genoa from wave motion. A unique work of its kind in engineering terms, in its final configuration it will be 6,200 metres long and will replace the existing breakwater, but will be positioned at a distance from the quay that will allow access to the port even for modern ships defined as 'Ultra large', which today suffer from limitations due to the reduced room for manoeuvre.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6e388d27-c215-4398-8371-2d7a9d0c17b7. The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.


Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

THỦ THUẬT HAY

Hướng dẫn tải và cài đặt Photoshop trên máy tính

Nhắc tới chỉnh sửa ảnh là nhắc tới Adobe Photoshop , nhờ những tính năng vượt trội cùng các công cụ chỉnh sửa chuyên nghiệp, phần mềm này sẽ giúp các bạn có thể biến những bức ảnh thô kệch, xấu xí của mình trở nên long

Top 9 mẹo vặt dành cho người dùng Gmail

Để trở thành một pro “Gmailer” bạn cần phải trang bị cho mình nhiều chiêu hơn nữa. Dưới đây là 10 mẹo vặt sử dụng Gmail mà ít ai biết.

Cách tối ưu hóa và có thêm không gian sử dụng iPhone

Đầu tiên, để xem được những ứng dụng đang sử dụng nhiều bộ nhớ nhất, bạn đọc cần vào Cài đặt -> Cài đặt chung -> Dung lượng iPhone. Dưới mỗi app, thiết bị sẽ thống kê thời gian lần cuối bạn sử dụng, từ đó bạn đọc

Hướng dẫn khắc phục lỗi "Some Update Were Cancelled" khi cập nhật Windows 10 thất bại

Không ít người dùng Fast Ring đã từng hoặc đang phải đối mặt với lỗi 'Some update were cancelled' khi nâng cấp lên những build mới, nhiều người dùng đang muốn cập nhật lên Windows 10 Redstone 3 build 16170 bị dính phải

Chia sẻ dữ liệu giữa điện thoại Android và PC

Android không có chương trình desktop giống như iTunes, vì vậy quá trình đồng bộ dữ liệu có thể không được rõ ràng như iPhone. Tuy nhiên, bạn không cần phải có ứng dụng đồng bộ desktop mà vẫn đạt mục đích.

ĐÁNH GIÁ NHANH

Đánh giá nhanh Camon CX: Thiết kế vỏ kim loại sang trọng, hiệu năng khá, sử dụng Android 7.0

Camon CX dễ dàng tạo được ấn tượng với người dùng bởi thiết kế nguyên khối cùng lớp vỏ kim loại sang trọng, hiệu năng khá tốt và đặc biệt là hỗ trợ nền tảng Android 7.0 với nhiều tính năng hấp dẫn

Giải mã sức hút của iPhone 13 Pro Max sau hơn 1 tháng ra mắt

Trong bộ tứ iPhone 13 vừa được Apple trình làng cách đây hơn 1 tháng, iPhone 13 Pro Max là bản cao cấp nhất và được chú ý nhiều nhất. Vậy sức hút của iPhone 13 Pro Max đến từ đâu mà nhiều người đặt mua đến vậy? iPhone