Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

MILAN, Italy, July 17, 2023 (GLOBE NEWSWIRE) -- In the 'underwater' construction site of the New Breakwater in Genoa, an important new phase of work is underway to consolidate the seabed. In the area identified as Test Area 1, the first gravel columns that will guarantee stability to the base on which the future barrier will rest have taken shape. The columns to be built are 70,000 and will run along the entire perimeter of the new dam. To date, approximately 100 columns have already been constructed. Within the first month, approximately 850 will be constructed, with the aim of completing them all within the next 17 months.

At the same time, the work of laying gravel on the seabed continues at full pace, where about 185,000 tonnes of material have already been laid, using a 3,600-tonne capacity ship and two smaller pontoons with a total capacity of about 700 tonnes, which carry an average of 3,000 tonnes of gravel per day and have already made a total of about 90 round trips, starting from Piombino and Genoa.

The New Breakwater is being built by the PERGENOVA BREAKWATER consortium, led by Webuild in cooperation with Fincantieri Infrastructure Opere Marittime, Fincosit and Sidra, while Rina is in charge of project management consulting. The work was commissioned by the Western Ligurian Sea Port System Authority. For the construction of the dam, which will also benefit from PNRR funding, it is estimated that one thousand people will be employed, including direct personnel and third parties.

The gravel columns will be built using an innovative technique known as the “Wet Top Feed – Blanket Method”. The technique involves the use of a vibrating probe, the vibroflot, a kind of needle between 17 and 21 metres long. The probe, attached to 40-metre-high cranes positioned on floating platforms, the pontoons, is brought to the seabed on which a layer of gravel thick enough to accommodate columns over 13 metres high has previously been placed. By vibrating and using combined water and air jets, the probe penetrates the ground and creates a tubular-shaped space into which the surrounding gravel material gradually slides. As the gravel slides, the future column takes shape and is progressively compacted.

The New Breakwater, the largest intervention ever carried out for the enhancement of Italy’s ports, is a barrier whose main task will be to protect the port of Genoa from wave motion. A unique work of its kind in engineering terms, in its final configuration it will be 6,200 metres long and will replace the existing breakwater, but will be positioned at a distance from the quay that will allow access to the port even for modern ships defined as 'Ultra large', which today suffer from limitations due to the reduced room for manoeuvre.

For more information:
Press Office LaPresse - ufficio.stampa@lapresse.it

A photo accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/6e388d27-c215-4398-8371-2d7a9d0c17b7. The photo is also available at Newscom, www.newscom.com, and via AP PhotoExpress.


Industry, Webuild: activities continue unabated at ‘underwater’ construction site of the new breakwater in Genoa

THỦ THUẬT HAY

Nên mua điều hòa hay quạt điều hòa?

Vào thời điểm nóng nực như thế này, các gia đình luôn muốn lựa chọn một thiết bị làm lạnh hiệu quả nhằm giúp cho căn phòng trở nên thoáng mát và dễ chịu hơn, theo đó, nhiều người dùng phân vân nên mua điều hòa hay quạt

Hướng dẫn các bước chia sẻ video Youtube từ điện thoại lên smart tivi Sony

Ngày nay, việc chia sẻ nội dung video Youtube lên smart tivi Sony không còn điều quá khó khăn nữa

Tips “ngon” tải Office 2016 full product key thành công 100%, hoạt động vĩnh viễn

Bộ ứng dụng văn phòng mới nhất hiện nay đó là Office 2016, được thiết kế để phục vụ cho những người đã quen thuộc với các phiên bản trước đó. Nó có nhiều cải tiến mạnh mẽ về chức năng và giao diện, đáp ứng đầy đủ nhu

10 cách khắc phục tình trạng Youtube chậm như sên những ngày đứt cáp

YouTube là một trong những trang web lưu trữ và chia sẻ video trực tuyến lớn nhất và được nhiều người yêu thích nhất hiện nay. Tuy nhiên trong quá trình xem video trên YouTube, khá nhiều người dùng than phiền về tốc độ

3 bước để kích hoạt mạng 4G cho tất cả các máy Android

Ngoài việc đổi sim 4G mới bạn cần thiết lập trên chiếc smartphone của mình để kích hoạt sử dụng. Cách thực hiện sau đây áp dụng cho toàn bộ máy Android.

ĐÁNH GIÁ NHANH

Đánh giá nhanh 3 chiếc smartphone đang "hot" nhất hiện nay

Thời gian gần đây 3 cái tên Galaxy Note 7 OPPO F1s và Lumia 830 đang thu hút sự quan tâm rất lớn của người dùng lẫn các bạn trẻ yêu công nghệ.

[MWC 2017] Đánh giá LG G6: Không còn mang người dùng ra thử nghiệm, LG đã đi đúng hướng hơn

Techrum - LG đã chính thức giới thiệu chiếc flagship mới nhất của hãng là G6 trong sự kiện thường niên MWC 2017. So với thế hệ tiền nhiệm, G6 có nhiều thay đổi rất lớn: ngoài từ bỏ thiết kế kiểu module vốn đã được thử

Cái kết “đắng lòng” khi thả rơi iPhone 13 Pro và iPhone 13 Pro Max nhiều lần

iPhone 13 Pro và iPhone 13 Pro Max được trang bị khung viền thép không gỉ, kính cường lực Ceramic Shield cao cấp. Tuy nhiên, với màn thả rơi iPhone 13 Pro và iPhone 13 Pro Max từ độ cao 2m và nhiều lần 2 máy đã bị